Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
42
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MS0218 # 03 Y:2002 | 03 | 2002 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $8,686 | $0 | Implemented |
MS0218 # 01 Y:2002 | 01 | 2002 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $11,278 | $10,000 | Not Implemented |
MS0218 # 06 Y:2002 | 06 | 2002 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,718 | $0 | Implemented |
MS0218 # 02 Y:2002 | 02 | 2002 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $9,569 | $0 | Implemented |
MS0218 # 05 Y:2002 | 05 | 2002 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $6,933 | $1,200 | Not Implemented |
MS0218 # 07 Y:2002 | 07 | 2002 | DISCONNECT BALLASTS | $2,405 | $1,230 | Implemented |
MS0218 # 04 Y:2002 | 04 | 2002 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,012 | $284 | Implemented |
GT0729 # 09 Y:2002 | 09 | 2002 | REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT | $235,152 | $156,000 | Not Implemented |
GT0729 # 08 Y:2002 | 08 | 2002 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $12,137 | $162,293 | Not Implemented |
GT0729 # 07 Y:2002 | 07 | 2002 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $693 | $1,198 | Not Implemented |
GT0729 # 06 Y:2002 | 06 | 2002 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,537 | $10,872 | Not Implemented |
GT0729 # 05 Y:2002 | 05 | 2002 | UPGRADE CONTROLS ON COMPRESSORS | $60 | $70 | Not Implemented |
GT0729 # 04 Y:2002 | 04 | 2002 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,990 | $1,450 | Not Implemented |
GT0729 # 03 Y:2002 | 03 | 2002 | MINIMIZE NON-ESSENTIAL MATERIAL IN HEAT TREATMENT PROCESS | $71,787 | $13,892 | n/a |
GT0729 # 02 Y:2002 | 02 | 2002 | PREHEAT COMBUSTION AIR WITH WASTE HEAT | $74,140 | $270,000 | n/a |
GT0729 # 01 Y:2002 | 01 | 2002 | PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER | $563,200 | $312,500 | Not Implemented |
MS0206 # 10 Y:2002 | 10 | 2002 | INSTALL TIMERS AND/OR THERMOSTATS | $867 | $708 | n/a |
MS0206 # 09 Y:2002 | 09 | 2002 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,327 | $1,088 | n/a |
MS0206 # 13 Y:2002 | 13 | 2002 | DISCONNECT BALLASTS | $213 | $150 | n/a |
MS0206 # 07 Y:2002 | 07 | 2002 | TURN OFF EQUIPMENT WHEN NOT IN USE | $2,925 | $80 | n/a |
MS0206 # 06 Y:2002 | 06 | 2002 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $3,757 | $4,120 | n/a |
MS0206 # 01 Y:2002 | 01 | 2002 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $28,045 | $7,508 | n/a |
MS0206 # 02 Y:2002 | 02 | 2002 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $8,945 | $8,000 | n/a |
MS0206 # 03 Y:2002 | 03 | 2002 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,351 | $23,103 | n/a |
MS0206 # 04 Y:2002 | 04 | 2002 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,335 | $189 | n/a |