Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
333
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
TA0019 # 02 Y:2001 | 02 | 2001 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $11,836 | $225 | Implemented |
TA0019 # 03 Y:2001 | 03 | 2001 | INSTALL PARTITIONS TO REDUCE SIZE OF CONDITIONED SPACE | $5,994 | $3,000 | Not Implemented |
TA0019 # 06 Y:2001 | 06 | 2001 | INSTALL / REPAIR INSULATION ON STEAM LINES | $161 | $140 | Not Implemented |
TA0019 # 04 Y:2001 | 04 | 2001 | USE EVAPORATION TO CONCENTRATE MATERIAL | $5,184 | $5,331 | Implemented |
TA0019 # 01 Y:2001 | 01 | 2001 | INSTALL AUTOMATIC PACKING EQUIPMENT | $27,478 | $2,805 | Not Implemented |
TA0019 # 05 Y:2001 | 05 | 2001 | INSTALL OCCUPANCY SENSORS | $1,015 | $346 | Implemented |
TA0020 # 06 Y:2001 | 06 | 2001 | INSULATE BARE EQUIPMENT | $685 | $140 | Implemented |
AM0404 # 08 Y:2001 | 08 | 2001 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $690 | $765 | Implemented |
AM0404 # 03 Y:2001 | 03 | 2001 | CONTRACT A WOOD PALLET RECYCLING COMPANY | $15,440 | $0 | Not Implemented |
AM0404 # 01 Y:2001 | 01 | 2001 | ELIMINATE OLD STOCK AND MODIFY INVENTORY CONTROL | $198,000 | $25,000 | Implemented |
AM0404 # 04 Y:2001 | 04 | 2001 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,330 | $41,800 | Implemented |
AM0404 # 02 Y:2001 | 02 | 2001 | REUSE RAGS UNTIL COMPLETELY SOILED | $12,600 | $0 | Implemented |
AM0404 # 05 Y:2001 | 05 | 2001 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,800 | $2,828 | Implemented |
TA0020 # 01 Y:2001 | 01 | 2001 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $16,175 | $26,460 | n/a |
AM0404 # 06 Y:2001 | 06 | 2001 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,710 | $368 | Implemented |
TA0020 # 03 Y:2001 | 03 | 2001 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $3,260 | $240 | Implemented |
TA0020 # 04 Y:2001 | 04 | 2001 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,415 | $1,715 | Implemented |
TA0020 # 08 Y:2001 | 08 | 2001 | INSULATE BARE EQUIPMENT | $370 | $160 | Implemented |
TA0020 # 02 Y:2001 | 02 | 2001 | PAY BILLS ON TIME TO AVOID LATE FEES | $4,751 | $0 | Implemented |
AM0404 # 07 Y:2001 | 07 | 2001 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $250 | $0 | Implemented |
TA0020 # 07 Y:2001 | 07 | 2001 | INSTALL OCCUPANCY SENSORS | $584 | $320 | Implemented |
TA0020 # 05 Y:2001 | 05 | 2001 | INSULATE BARE EQUIPMENT | $1,110 | $321 | Implemented |
AM0403 # 07 Y:2001 | 07 | 2001 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $7,050 | $5,890 | Implemented |
AM0403 # 11 Y:2001 | 11 | 2001 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $900 | $0 | Implemented |
AM0403 # 12 Y:2001 | 12 | 2001 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $380 | $0 | Implemented |