IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

69

matching recommendations
Reset
NAICS 333 Machinery Manufacturing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
UU0138 # 05 Y:2018 05 2018 INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT $615 $0 Implemented
UU0138 # 04 Y:2018 04 2018 INSTALL OCCUPANCY SENSORS $1,089 $1,500 Implemented
UU0138 # 03 Y:2018 03 2018 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $1,911 $0 Implemented
UU0138 # 02 Y:2018 02 2018 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $9,044 $2,760 Implemented
UU0138 # 01 Y:2018 01 2018 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $14,221 $18,137 Implemented
BS0076 # 06 Y:2016 06 2016 INSULATE BARE EQUIPMENT $655 $768 Implemented
BS0076 # 01 Y:2016 01 2016 OPTIMIZE PLANT POWER FACTOR $14,626 $14,109 Not Implemented
BS0076 # 02 Y:2016 02 2016 UPGRADE CONTROLS ON COMPRESSORS $5,025 $2,777 Implemented
BS0076 # 03 Y:2016 03 2016 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $1,367 $1,665 Implemented
BS0076 # 04 Y:2016 04 2016 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS $962 $14 Implemented
BS0076 # 05 Y:2016 05 2016 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $737 $871 Implemented
BS0076 # 07 Y:2016 07 2016 TURN OFF EQUIPMENT WHEN NOT IN USE $612 $440 Implemented
UU0108 # 02 Y:2006 02 2006 USE DEMAND CONTROLLER OR LOAD SHEDDER $28,070 $10,000 Not Implemented
UU0108 # 03 Y:2006 03 2006 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $14,560 $2,670 Not Implemented
UU0108 # 04 Y:2006 04 2006 RECOVER WASTE HEAT FROM EQUIPMENT $2,120 $4,365 Not Implemented
UU0108 # 05 Y:2006 05 2006 INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS $9,940 $30,000 Not Implemented
UU0108 # 01 Y:2006 01 2006 OPTIMIZE PLANT POWER FACTOR $3,970 $3,720 Not Implemented
UU0107 # 02 Y:2006 02 2006 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $950 $18 Not Implemented
UU0107 # 06 Y:2006 06 2006 OPTIMIZE PLANT POWER FACTOR $1,690 $1,860 Not Implemented
UU0107 # 05 Y:2006 05 2006 USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE $1,470 $8,820 Not Implemented
UU0107 # 04 Y:2006 04 2006 REPLACE BOILER $1,090 $800 Not Implemented
UU0107 # 03 Y:2006 03 2006 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,590 $2,085 Not Implemented
UU0107 # 01 Y:2006 01 2006 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $520 $435 Not Implemented
UU0104 # 06 Y:2006 06 2006 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $15,650 $28,400 Not Implemented
UU0104 # 07 Y:2006 07 2006 OPTIMIZE PLANT POWER FACTOR $3,510 $8,490 Not Implemented