Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
75
matching recommendationsSIC | 49 | Electric, Gas, And Sanitary Services |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UU0250 # 02 Y:2024 | 02 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $18,742 | $49,723 | n/a |
UU0250 # 04 Y:2024 | 04 | 2024 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $8,795 | $5,760 | n/a |
UU0250 # 06 Y:2024 | 06 | 2024 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $6,753 | $5,720 | n/a |
UU0250 # 01 Y:2024 | 01 | 2024 | OPTIMIZE PLANT POWER FACTOR | $42,332 | $60,420 | n/a |
UU0250 # 05 Y:2024 | 05 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,806 | $13,208 | n/a |
UU0250 # 03 Y:2024 | 03 | 2024 | BURN A LESS EXPENSIVE GRADE OF FUEL | $11,024 | $16,000 | n/a |
UU0203 # 03 Y:2022 | 03 | 2022 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $3,080 | $10,070 | Not Implemented |
UU0203 # 02 Y:2022 | 02 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $19,358 | $60,000 | Not Implemented |
UU0203 # 01 Y:2022 | 01 | 2022 | USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY | $33,490 | $103,200 | Not Implemented |
UU0200 # 03 Y:2022 | 03 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,392 | $5,232 | Implemented |
UU0200 # 02 Y:2022 | 02 | 2022 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $3,992 | $10,000 | Not Implemented |
UU0200 # 01 Y:2022 | 01 | 2022 | USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY | $41,228 | $52,800 | Not Implemented |
UU0197 # 04 Y:2022 | 04 | 2022 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $12,230 | $4,000 | Implemented |
UU0197 # 03 Y:2022 | 03 | 2022 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $10,900 | $3,000 | Implemented |
UU0197 # 02 Y:2022 | 02 | 2022 | DEMOLISH OLD BUILDING TO REDUCE TAX AND INSURANCE BILLS | $12,033 | $300 | Implemented |
UU0197 # 05 Y:2022 | 05 | 2022 | OPTIMIZE PLANT POWER FACTOR | $1,591 | $6,000 | Not Implemented |
UU0197 # 06 Y:2022 | 06 | 2022 | DEMOLISH OLD BUILDING TO REDUCE TAX AND INSURANCE BILLS | $130 | $25 | Implemented |
UU0197 # 07 Y:2022 | 07 | 2022 | USE OPTIMUM TEMPERATURE | $380 | $200 | Not Implemented |
UU0197 # 01 Y:2022 | 01 | 2022 | USE POWER DURING OFF-PEAK PERIODS | $13,098 | $10,000 | Implemented |
UU0182 # 05 Y:2021 | 05 | 2021 | INSULATE BARE EQUIPMENT | $5,611 | $2,229 | Not Implemented |
UU0182 # 02 Y:2021 | 02 | 2021 | LEVEL TWO – INSTALL CONTROL SYSTEM USING IIOT DEVICES WITH COMMUNICATION CAPABILITIES TO STORE DATA TO THE CLOUD | $301,212 | $427,040 | Implemented |
UU0182 # 03 Y:2021 | 03 | 2021 | USE WASTE HEAT WITH A CLOSED-CYCLE GAS TURBINE-GENERATOR SET TO COGENERATE ELECTRICITY AND HEAT | $94,872 | $621,000 | Not Implemented |
UU0182 # 04 Y:2021 | 04 | 2021 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $69,301 | $172,000 | Not Implemented |
UU0182 # 06 Y:2021 | 06 | 2021 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $4,360 | $920 | Implemented |
UU0182 # 01 Y:2021 | 01 | 2021 | SELL COMBUSTIBLE WASTE | $358,314 | $840,585 | Implemented |