Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
74
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UU0139 # 04 Y:2018 | 04 | 2018 | INSTALL TIMERS AND/OR THERMOSTATS | $446 | $100 | Implemented |
UU0139 # 03 Y:2018 | 03 | 2018 | USE PHOTOCELL CONTROLS | $4,082 | $2,275 | Implemented |
UU0139 # 02 Y:2018 | 02 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,262 | $20,223 | Implemented |
UU0139 # 01 Y:2018 | 01 | 2018 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $51,858 | $44,642 | Implemented |
UU0138 # 06 Y:2018 | 06 | 2018 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $599 | $150 | Implemented |
UU0138 # 05 Y:2018 | 05 | 2018 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $615 | $0 | Implemented |
UU0138 # 04 Y:2018 | 04 | 2018 | INSTALL OCCUPANCY SENSORS | $1,089 | $1,500 | Implemented |
UU0138 # 03 Y:2018 | 03 | 2018 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $1,911 | $0 | Implemented |
UU0138 # 02 Y:2018 | 02 | 2018 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $9,044 | $2,760 | Implemented |
UU0138 # 01 Y:2018 | 01 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,221 | $18,137 | Implemented |
UU0137 # 05 Y:2018 | 05 | 2018 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $11,310 | $7,650 | Implemented |
UU0137 # 01 Y:2018 | 01 | 2018 | RECOVER WASTE HEAT FROM EQUIPMENT | $48,448 | $23,000 | Not Implemented |
UU0137 # 02 Y:2018 | 02 | 2018 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $37,021 | $24,600 | Implemented |
UU0137 # 03 Y:2018 | 03 | 2018 | RECOVER WASTE HEAT FROM EQUIPMENT | $26,521 | $17,000 | Implemented |
UU0137 # 04 Y:2018 | 04 | 2018 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $11,622 | $7,600 | Implemented |
UU0137 # 06 Y:2018 | 06 | 2018 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $973 | $3,500 | Implemented |
UU0136 # 07 Y:2018 | 07 | 2018 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,814 | $600 | Implemented |
UU0136 # 01 Y:2018 | 01 | 2018 | USE WASTE HEAT WITH A CLOSED-CYCLE GAS TURBINE-GENERATOR SET TO COGENERATE ELECTRICITY AND HEAT | $159,197 | $1,737,000 | Not Implemented |
UU0136 # 02 Y:2018 | 02 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $17,936 | $17,716 | Implemented |
UU0136 # 03 Y:2018 | 03 | 2018 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $14,124 | $0 | Not Implemented |
UU0136 # 04 Y:2018 | 04 | 2018 | INSTALL SPECTRAL REFLECTORS / DELAMP | $5,731 | $1,000 | Not Implemented |
UU0136 # 06 Y:2018 | 06 | 2018 | TURN OFF EQUIPMENT WHEN NOT IN USE | $2,075 | $0 | Implemented |
UU0136 # 08 Y:2018 | 08 | 2018 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $1,192 | $1,000 | Not Implemented |
UU0136 # 05 Y:2018 | 05 | 2018 | USE PHOTOCELL CONTROLS | $4,948 | $420 | Implemented |
UU0135 # 01 Y:2018 | 01 | 2018 | PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER | $10,541 | $800 | Not Implemented |