Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Bradley University |
---|---|
Assessment Year | 2001 |
Principal Product | Rubber Hose and Mixed Rubber |
NAICS | n/a |
SIC | 3052 - Rubber & Plastics Hose & Belting |
Sales | $10,000,000-$50,000,000 |
# of Employees | 430 |
Plant Area (Sq.Ft.) | 445,200 |
Annual Production | 90,000,000 Pounds |
Production Hrs. Annual | 8,760 |
Location (State) | IL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $990,782 | 32,920,307 | kWh | $0.03 |
Electricity Demand | $564,156 | 59,218 | kW-months/year | $9.53 |
Electricity Fees | $53,006 | - | $ | - |
Natural Gas | $546,657 | 117,519 | MMBtu | $4.65 |
TOTAL ENERGY COSTS | $2,249,500 | |||
RECOMMENDED SAVINGS* | $422,796 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $46,130 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Administrative Changes | Ancillary Material Cost | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Administrative Changes | Ancillary Material Cost | One-time Revenue or Avoided Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | $ | $ | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.1123 INSTALL AUTOMATIC STACK DAMPER |
Savings: $38,189 Cost: $15,000 |
- | - | - | - | $38,189 | 8,324 | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$38,189 8,324 MMBtu |
- - lb |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7231 USE RADIANT HEATER FOR SPOT HEATING |
Savings: $25,600 Cost: $45,600 |
- | - | - | - | $25,600 | 5,647 | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$25,600 5,647 MMBtu |
- - lb |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE |
Savings: $24,024 Cost: $16,000 |
$15,027 | 499,246 | $8,997 | 944 | - | - | - | - | - | - | - | - | - | - |
$15,027 499,246 kWh |
$8,997 944 kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $19,936 Cost: $700 |
$12,293 | 418,174 | $7,643 | 802 | - | - | - | - | - | - | - | - | - | - |
$12,293 418,174 kWh |
$7,643 802 kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $17,090 Cost: $40,260 |
$12,876 | 427,786 | $4,214 | 442 | - | - | - | - | - | - | - | - | - | - |
$12,876 427,786 kWh |
$4,214 442 kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS |
Savings: $5,069 Cost: $5,000 |
$2,834 | 94,140 | $1,932 | 203 | - | - | - | - | - | - | - | - | $303 | - |
$2,834 94,140 kWh |
$1,932 203 kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - $ |
$303 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $4,608 Cost: $4,200 |
$2,371 | 78,643 | $2,237 | 235 | - | - | - | - | - | - | - | - | - | - |
$2,371 78,643 kWh |
$2,237 235 kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $3,749 Cost: $1,000 |
$2,615 | 86,893 | $1,134 | 119 | - | - | - | - | - | - | - | - | - | - |
$2,615 86,893 kWh |
$1,134 119 kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.3132 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS |
Savings: $2,745 Cost: - |
- | - | $2,745 | 288 | - | - | - | - | - | - | - | - | - | - |
- - kWh |
$2,745 288 kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $477 Cost: $555 |
$170 | 5,659 | $74 | 8 | - | - | - | - | - | - | - | - | $233 | - |
$170 5,659 kWh |
$74 8 kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - $ |
$233 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 3.5217 REUSE / RECYCLE/ SELL PAPER PRODUCTS |
Savings: $14,925 Cost: $1,000 |
- | - | - | - | - | - | $14,925 | 398,000 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$14,925 398,000 lb |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12: 3.5316 CONTRACT A WOOD PALLET RECYCLING COMPANY |
Savings: $6,200 Cost: $321 |
- | - | - | - | - | - | - | - | - | - | $6,200 | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
- - $ |
$6,200 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
13: 3.5315 LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER |
Savings: $2,656 Cost: $1,000 |
- | - | - | - | - | - | $2,656 | 66,400 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$2,656 66,400 lb |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
14: 4.811 DEMOLISH OLD BUILDING TO REDUCE TAX AND INSURANCE BILLS |
Savings: $200,000 Cost: $50,000 |
- | - | - | - | - | - | - | - | - | - | - | - | $200,000 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - $ |
$200,000 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
15: 4.521 CLEAR AND RENT EXISTING SPACE |
Savings: $57,528 Cost: $10,000 |
- | - | - | - | - | - | - | - | $57,528 | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
$57,528 - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $422,796 Cost: $190,636 |
$48,186 | 1,610,541 | $28,976 | 3,041 | $63,789 | 13,971 | $17,581 | 464,400 | $57,528 | - | $6,200 | - | $200,536 | - | $48,186 1,610,541 kWh |
$28,976 3,041 kW-months/year |
$63,789 13,971 MMBtu |
$17,581 464,400 lb |
$57,528 - $ |
$6,200 - $ |
$200,536 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $46,130 Cost: $7,021 |
$15,127 | 512,314 | $9,575 | 1,005 | - | - | $14,925 | 398,000 | - | - | $6,200 | - | $303 | - | $15,127 512,314 kWh |
$9,575 1,005 kW-months/year |
- - MMBtu |
$14,925 398,000 lb |
- - $ |
$6,200 - $ |
$303 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | $ | $ | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Administrative Changes | Ancillary Material Cost | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Administrative Changes | Ancillary Material Cost | One-time Revenue or Avoided Cost |