Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Bradley University |
---|---|
Assessment Year | 2001 |
Principal Product | Platic Bottles |
NAICS | n/a |
SIC | 3089 - Plastics Products, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 100 |
Plant Area (Sq.Ft.) | 75,000 |
Annual Production | 400,000,000 Pieces |
Production Hrs. Annual | 8,112 |
Location (State) | IL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $621,711 | 16,892,380 | kWh | $0.04 |
Electricity Demand | $434,646 | 30,537 | kW-months/year | $14.23 |
Electricity Fees | $2,957 | - | $ | - |
Natural Gas | $13,599 | 3,540 | MMBtu | $3.84 |
TOTAL ENERGY COSTS | $1,092,755 | |||
RECOMMENDED SAVINGS* | $79,524 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $42,856 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Administrative Changes | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Administrative Changes | One-time Revenue or Avoided Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | lb | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $21,189 Cost: $48,040 |
$14,828 | 402,923 | $6,361 | 447 | - | - | - | - | - | - |
$14,828 402,923 kWh |
$6,361 447 kW-months/year |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE |
Savings: $10,311 Cost: $23,500 |
$6,559 | 178,244 | $3,752 | 264 | - | - | - | - | - | - |
$6,559 178,244 kWh |
$3,752 264 kW-months/year |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $5,362 Cost: $2,000 |
$3,411 | 92,681 | $1,951 | 137 | - | - | - | - | - | - |
$3,411 92,681 kWh |
$1,951 137 kW-months/year |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2691 SHUT OFF COOLING IF COLD OUTSIDE AIR WILL COOL PROCESS |
Savings: $5,279 Cost: $500 |
$3,469 | 93,462 | $1,810 | 127 | - | - | - | - | - | - |
$3,469 93,462 kWh |
$1,810 127 kW-months/year |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.3134 SHIFT FROM DAYTIME TO NIGHTTIME OPERATION |
Savings: $2,929 Cost: $500 |
- | - | $2,929 | 206 | - | - | - | - | - | - |
- - kWh |
$2,929 206 kW-months/year |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $1,849 Cost: $1,275 |
$728 | 19,769 | $1,121 | 79 | - | - | - | - | - | - |
$728 19,769 kWh |
$1,121 79 kW-months/year |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $390 Cost: $355 |
$147 | 3,995 | $78 | 6 | - | - | - | - | $165 | - |
$147 3,995 kWh |
$78 6 kW-months/year |
- - lb |
- - $ |
$165 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 3.5212 REGRIND, REUSE, OR SELL SCRAP PLASTIC PARTS |
Savings: $15,600 Cost: $2,960 |
- | - | - | - | $15,600 | 1,560,000 | - | - | - | - |
- - kWh |
- - kW-months/year |
$15,600 1,560,000 lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 4.441 INSTALL AUTOMATIC PACKING EQUIPMENT |
Savings: $10,843 Cost: $31,000 |
- | - | - | - | - | - | $10,843 | - | - | - |
- - kWh |
- - kW-months/year |
- - lb |
$10,843 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 4.447 AUTOMATE PAYROLL SYSTEM |
Savings: $5,772 Cost: $3,000 |
- | - | - | - | - | - | $5,772 | - | - | - |
- - kWh |
- - kW-months/year |
- - lb |
$5,772 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $79,524 Cost: $113,130 |
$29,142 | 791,074 | $18,002 | 1,266 | $15,600 | 1,560,000 | $16,615 | - | $165 | - | $29,142 791,074 kWh |
$18,002 1,266 kW-months/year |
$15,600 1,560,000 lb |
$16,615 - $ |
$165 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $42,856 Cost: $39,460 |
$6,880 | 186,143 | $3,761 | 264 | $15,600 | 1,560,000 | $16,615 | - | - | - | $6,880 186,143 kWh |
$3,761 264 kW-months/year |
$15,600 1,560,000 lb |
$16,615 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | lb | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Administrative Changes | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Administrative Changes | One-time Revenue or Avoided Cost |