IAC Assessment: BD0464
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: BD0464
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Bradley University
Assessment Year 2015
Principal Product Baked goods
NAICS 311919 - Other Snack Food Manufacturing
SIC 2052 - Cookies And Crackers
Sales $50,000,000-$100,000,000
# of Employees 375
Plant Area (Sq.Ft.) 290,000
Annual Production 50,000,000 Pieces
Production Hrs. Annual 8,760
Location (State) IL
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $324,664 5,103,289 kWh $0.06
Electricity Demand $71,841 11,850 kW-months/year $6.06
Electricity Fees $10,199 - $ -
Natural Gas $229,709 33,505 MMBtu $6.86
TOTAL ENERGY COSTS $636,413
RECOMMENDED SAVINGS* $48,708 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $22,698
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Personnel Changes Ancillary Material Cost Electricity Usage Electricity Demand Natural Gas Personnel Changes Ancillary Material Cost
$ kWh $ kW-months/year $ MMBtu $ $ $ $
01: 2.2442 PREHEAT COMBUSTION AIR WITH WASTE HEAT Savings:
$12,126
Cost:
$18,000
$(-7,481) (-117,629) $(-976) (-161) $20,583 3,116 - - - - $(-7,481)
(-117,629)
kWh
$(-976)
(-161)
kW-months/year
$20,583
3,116
MMBtu
-
-
$
-
-
$
02: 2.4226 USE / PURCHASE OPTIMUM SIZED COMPRESSOR Savings:
$11,746
Cost:
$20,000
$10,390 163,374 $1,356 224 - - - - - - $10,390
163,374
kWh
$1,356
224
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
03: 2.1221 REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES Savings:
$9,022
Cost:
$30,000
- - - - $9,022 1,366 - - - - -
-
kWh
-
-
kW-months/year
$9,022
1,366
MMBtu
-
-
$
-
-
$
04: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$6,685
Cost:
$3,075
$5,659 88,976 $1,026 169 - - - - - - $5,659
88,976
kWh
$1,026
169
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
05: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS Savings:
$3,866
Cost:
$20
- - $3,866 638 - - - - - - -
-
kWh
$3,866
638
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
06: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$2,364
Cost:
$2,900
$2,081 32,723 $283 47 - - - - - - $2,081
32,723
kWh
$283
47
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
07: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$1,313
Cost:
$750
$1,161 18,258 $152 25 - - - - - - $1,161
18,258
kWh
$152
25
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
08: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$996
Cost:
$700
$550 8,655 $72 12 - - $153 - $221 - $550
8,655
kWh
$72
12
kW-months/year
-
-
MMBtu
$153
-
$
$221
-
$
09: 2.6214 SHUT OFF PILOTS IN STANDBY EQUIPMENT Savings:
$590
Cost:
$40
- - - - $590 89 - - - - -
-
kWh
-
-
kW-months/year
$590
89
MMBtu
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$48,708
Cost:
$75,485
$12,360 194,357 $5,779 954 $30,195 4,572 $153 - $221 - $12,360
194,357
kWh
$5,779
954
kW-months/year
$30,195
4,572
MMBtu
$153
-
$
$221
-
$
TOTAL IMPLEMENTED Savings:
$22,698
Cost:
$26,765
$19,291 303,331 $2,817 465 $590 89 - - - - $19,291
303,331
kWh
$2,817
465
kW-months/year
$590
89
MMBtu
-
-
$
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ $ $ $
Electricity Usage Electricity Demand Natural Gas Personnel Changes Ancillary Material Cost Electricity Usage Electricity Demand Natural Gas Personnel Changes Ancillary Material Cost