Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Texas A&M, Kingsville |
---|---|
Assessment Year | 1996 |
Principal Product | processed meat |
NAICS | n/a |
SIC | 2013 - Sausages And Other Prepared Meats |
Sales | $10,000,000-$50,000,000 |
# of Employees | 100 |
Plant Area (Sq.Ft.) | 25,519 |
Annual Production | 24,000,000 Pounds |
Production Hrs. Annual | 3,120 |
Location (State) | TX |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $62,141 | 1,963,658 | kWh | $0.03 |
Electricity Demand | $59,179 | 4,195 | kW-months/year | $14.11 |
Electricity Fees | $706 | - | $ | - |
Natural Gas | $10,145 | 3,426 | MMBtu | $2.96 |
TOTAL ENERGY COSTS | $134,901 | |||
RECOMMENDED SAVINGS* | $85,837 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $68,017 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Solid Waste (non-haz) | Primary Raw Material | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Solid Waste (non-haz) | Primary Raw Material | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | lb | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS |
Savings: $490 Cost: $430 |
$168 | 5,862 | $322 | 24 | - | - | - | - | - | - | - | - |
$168 5,862 kWh |
$322 24 kW-months/year |
- - MMBtu |
- - Tgal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $6,320 Cost: $7,240 |
$2,627 | 92,321 | $3,693 | 264 | - | - | - | - | - | - | - | - |
$2,627 92,321 kWh |
$3,693 264 kW-months/year |
- - MMBtu |
- - Tgal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.6242 MINIMIZE OPERATION OF EQUIPMENT MAINTAINED IN STANDBY CONDITION |
Savings: $5,273 Cost: $150 |
- | - | - | - | $5,273 | 1,781 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$5,273 1,781 MMBtu |
- - Tgal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7442 KEEP DOORS AND WINDOWS SHUT WHEN NOT ON USE |
Savings: $2,264 Cost: $800 |
$2,264 | 79,426 | - | - | - | - | - | - | - | - | - | - |
$2,264 79,426 kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4314 USE SYNTHETIC LUBRICANT |
Savings: $1,339 Cost: - |
$461 | 16,120 | $878 | 60 | - | - | - | - | - | - | - | - |
$461 16,120 kWh |
$878 60 kW-months/year |
- - MMBtu |
- - Tgal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $717 Cost: $129 |
$260 | 9,086 | $457 | 36 | - | - | - | - | - | - | - | - |
$260 9,086 kWh |
$457 36 kW-months/year |
- - MMBtu |
- - Tgal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $470 Cost: $40 |
$148 | 5,275 | $322 | 24 | - | - | - | - | - | - | - | - |
$148 5,275 kWh |
$322 24 kW-months/year |
- - MMBtu |
- - Tgal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $934 Cost: $273 |
- | - | - | - | $934 | 389 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$934 389 MMBtu |
- - Tgal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $265 Cost: $150 |
$265 | 9,379 | - | - | - | - | - | - | - | - | - | - |
$265 9,379 kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $79 Cost: $260 |
$79 | 879 | - | - | - | - | - | - | - | - | - | - |
$79 879 kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 3.1191 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS |
Savings: $49,350 Cost: $13,000 |
- | - | - | - | - | - | - | - | - | - | $49,350 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
- - lb |
$49,350 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12: 3.5311 RECOVER AND REUSE WASTE MATERIAL |
Savings: $9,606 Cost: $3,000 |
- | - | - | - | - | - | - | - | $9,606 | 1,300 | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
$9,606 1,300 lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
13: 3.5311 RECOVER AND REUSE WASTE MATERIAL |
Savings: $5,829 Cost: $1,000 |
- | - | - | - | - | - | - | - | $5,829 | 26,000 | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
$5,829 26,000 lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
14: 3.4154 ELIMINATE LEAKS IN WATER LINES AND VALVES |
Savings: $2,901 Cost: $150 |
- | - | - | - | - | - | $2,901 | 539,225 | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$2,901 539,225 Tgal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $85,837 Cost: $26,622 |
$6,272 | 218,348 | $5,672 | 408 | $6,207 | 2,170 | $2,901 | 539,225 | $15,435 | 27,300 | $49,350 | - | $6,272 218,348 kWh |
$5,672 408 kW-months/year |
$6,207 2,170 MMBtu |
$2,901 539,225 Tgal |
$15,435 27,300 lb |
$49,350 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $68,017 Cost: $15,639 |
$3,329 | 114,890 | $1,335 | 96 | $5,273 | 1,781 | $2,901 | 539,225 | $5,829 | 26,000 | $49,350 | - | $3,329 114,890 kWh |
$1,335 96 kW-months/year |
$5,273 1,781 MMBtu |
$2,901 539,225 Tgal |
$5,829 26,000 lb |
$49,350 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | lb | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Solid Waste (non-haz) | Primary Raw Material | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Solid Waste (non-haz) | Primary Raw Material |