Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | North Carolina State |
---|---|
Assessment Year | 2004 |
Principal Product | Knit hosiery and active wear |
NAICS | 315110 - Hosiery and Sock Mills |
SIC | 2252 - Hosiery, Nec |
Sales | $5,000,000-$10,000,000 |
# of Employees | 92 |
Plant Area (Sq.Ft.) | 100,000 |
Annual Production | 18,000,000 Pieces |
Production Hrs. Annual | 6,000 |
Location (State) | NC |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $94,204 | 2,006,550 | kWh | $0.05 |
Electricity Demand | $41,857 | 7,372 | kW-months/year | $5.68 |
Electricity Fees | $5,414 | - | $ | - |
Natural Gas | $93,905 | 10,098 | MMBtu | $9.30 |
TOTAL ENERGY COSTS | $254,906 | |||
RECOMMENDED SAVINGS* | $45,937 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $14,732 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Personnel Changes | Administrative Changes | Ancillary Material Cost | Primary Product | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Personnel Changes | Administrative Changes | Ancillary Material Cost | Primary Product | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | $ | $ | $ | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 4.113 INSTALL REFRIGERATION SYSTEM TO COOL PRODUCT |
Savings: $9,750 Cost: - |
$(-1,632) | (-28,740) | - | - | - | - | - | - | - | - | $(-468) | - | - | - | $11,850 | - |
$(-1,632) (-28,740) kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
$(-468) - $ |
- - $ |
$11,850 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE |
Savings: $8,603 Cost: $1,000 |
- | - | $8,603 | - | - | - | - | - | - | - | - | - | - | - | - | - |
- - kWh |
$8,603 - kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.1133 ADJUST BURNERS FOR EFFICIENT OPERATION |
Savings: $1,163 Cost: $800 |
- | - | - | - | $1,163 | 125 | - | - | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$1,163 125 MMBtu |
- - Tgal |
- - $ |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.1242 MINIMIZE BOILER BLOWDOWN WITH BETTER FEEDWATER TREATMENT |
Savings: $1,175 Cost: $1,200 |
- | - | - | - | - | - | $375 | 75,758 | - | - | $500 | - | $300 | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$375 75,758 Tgal |
- - $ |
$500 - $ |
$300 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.1333 CONVERT COMBUSTION EQUIPMENT TO BURN OIL |
Savings: $21,805 Cost: $15,800 |
- | - | - | - | $21,805 | - | - | - | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$21,805 - MMBtu |
- - Tgal |
- - $ |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.2121 INCREASE AMOUNT OF CONDENSATE RETURNED |
Savings: $1,388 Cost: $900 |
- | - | - | - | $1,388 | 149 | - | - | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$1,388 149 MMBtu |
- - Tgal |
- - $ |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES |
Savings: $1,037 Cost: $1,335 |
- | - | - | - | $1,037 | 112 | - | - | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$1,037 112 MMBtu |
- - Tgal |
- - $ |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $797 Cost: $1,315 |
$492 | 16,221 | $305 | 32 | - | - | - | - | - | - | - | - | - | - | - | - |
$492 16,221 kWh |
$305 32 kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $219 Cost: $100 |
$357 | 11,778 | $222 | 24 | - | - | - | - | $(-160) | - | - | - | $(-200) | - | - | - |
$357 11,778 kWh |
$222 24 kW-months/year |
- - MMBtu |
- - Tgal |
$(-160) - $ |
- - $ |
$(-200) - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $45,937 Cost: $22,450 |
$(-783) | (-741) | $9,130 | 56 | $25,393 | 386 | $375 | 75,758 | $(-160) | - | $32 | - | $100 | - | $11,850 | - | $(-783) (-741) kWh |
$9,130 56 kW-months/year |
$25,393 386 MMBtu |
$375 75,758 Tgal |
$(-160) - $ |
$32 - $ |
$100 - $ |
$11,850 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $14,732 Cost: $4,335 |
$(-1,275) | (-16,962) | $222 | 24 | $3,588 | 386 | $375 | 75,758 | $(-160) | - | $32 | - | $100 | - | $11,850 | - | $(-1,275) (-16,962) kWh |
$222 24 kW-months/year |
$3,588 386 MMBtu |
$375 75,758 Tgal |
$(-160) - $ |
$32 - $ |
$100 - $ |
$11,850 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | $ | $ | $ | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Personnel Changes | Administrative Changes | Ancillary Material Cost | Primary Product | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Personnel Changes | Administrative Changes | Ancillary Material Cost | Primary Product |