IAC Assessment: NC0382
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: NC0382
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center North Carolina State
Assessment Year 2008
Principal Product Paints
NAICS 325510 - Paint and Coating Manufacturing
SIC 2851 - Paints And Allied Products
Sales $10,000,000-$50,000,000
# of Employees 130
Plant Area (Sq.Ft.) 300,000
Annual Production 6,000 Thousand Gallons
Production Hrs. Annual 8,600
Location (State) NC
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $234,133 76,860,000 kWh $0.00
Electricity Demand $136,614 14,376 kW-months/year $9.50
Electricity Fees $9,515 - $ -
Natural Gas $201,166 17,445 MMBtu $11.53
TOTAL ENERGY COSTS $581,428
RECOMMENDED SAVINGS* $27,986 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $7,817
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Personnel Changes Administrative Changes Electricity Usage Electricity Demand Natural Gas Personnel Changes Administrative Changes
$ kWh $ kW-months/year $ MMBtu $ $ $ $
01: 2.133 Alternate Fuel Savings:
$1,350
Cost:
$1,000
- - - - $1,350 118 - - - - -
-
kWh
-
-
kW-months/year
$1,350
118
MMBtu
-
-
$
-
-
$
02: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS Savings:
$8,305
Cost:
$8,000
$812 - $7,493 895 - - - - - - $812
-
kWh
$7,493
895
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
03: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT Savings:
$11,864
Cost:
$6,150
- - - - $11,864 1,029 - - - - -
-
kWh
-
-
kW-months/year
$11,864
1,029
MMBtu
-
-
$
-
-
$
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$2,333
Cost:
$100
$2,333 76,987 $900 107 - - $(-600) - $(-300) - $2,333
76,987
kWh
$900
107
kW-months/year
-
-
MMBtu
$(-600)
-
$
$(-300)
-
$
05: 2.3132 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS Savings:
$1,226
Cost:
-
$262 - $964 115 - - - - - - $262
-
kWh
$964
115
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
06: 2.4151 DEVELOP A REPAIR/REPLACE POLICY Savings:
$1,644
Cost:
$2,483
$1,187 39,148 $457 55 - - - - - - $1,187
39,148
kWh
$457
55
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,264
Cost:
$4,408
$906 30,100 $358 42 - - - - - - $906
30,100
kWh
$358
42
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$27,986
Cost:
$22,141
$5,500 146,235 $10,172 1,214 $13,214 1,147 $(-600) - $(-300) - $5,500
146,235
kWh
$10,172
1,214
kW-months/year
$13,214
1,147
MMBtu
$(-600)
-
$
$(-300)
-
$
TOTAL IMPLEMENTED Savings:
$7,817
Cost:
$7,991
$4,688 146,235 $2,679 319 $1,350 118 $(-600) - $(-300) - $4,688
146,235
kWh
$2,679
319
kW-months/year
$1,350
118
MMBtu
$(-600)
-
$
$(-300)
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ $ $ $
Electricity Usage Electricity Demand Natural Gas Personnel Changes Administrative Changes Electricity Usage Electricity Demand Natural Gas Personnel Changes Administrative Changes