Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Texas, Arlington |
---|---|
Assessment Year | 2001 |
Principal Product | Business Forms |
NAICS | n/a |
SIC | 2764 - |
Sales | $10,000,000-$50,000,000 |
# of Employees | 99 |
Plant Area (Sq.Ft.) | 104,850 |
Annual Production | 3,400,000 Pounds |
Production Hrs. Annual | 6,048 |
Location (State) | TX |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $91,781 | 2,455,500 | kWh | $0.04 |
Electricity Demand | $48,289 | 5,953 | kW-months/year | $8.11 |
Natural Gas | $1,881 | 298 | MMBtu | $6.31 |
TOTAL ENERGY COSTS | $145,061 | |||
RECOMMENDED SAVINGS* | $22,446 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $13,397 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Water Disposal | Other Liquid (non-haz) | Electricity Usage | Electricity Demand | Water Disposal | Other Liquid (non-haz) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | Tgal | $ | gal | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.6222 USE DRYING OVEN (BATCH TYPE) ON ALTERNATE DAYS OR OTHER OPTIMUM SCHEDULE TO RUN EQUIPMENT WITH FULL LOADS |
Savings: $6,177 Cost: $2,016 |
- | - | $6,177 | 42 | - | - | - | - |
- - kWh |
$6,177 42 kW-months/year |
- - Tgal |
- - gal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 3.6192 USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL |
Savings: $3,272 Cost: - |
- | - | - | - | $3,272 | - | - | - |
- - kWh |
- - kW-months/year |
$3,272 - Tgal |
- - gal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $3,184 Cost: $1,049 |
$1,466 | 56,380 | $1,718 | 138 | - | - | - | - |
$1,466 56,380 kWh |
$1,718 138 kW-months/year |
- - Tgal |
- - gal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.5316 CONTRACT A WOOD PALLET RECYCLING COMPANY |
Savings: $3,110 Cost: - |
- | - | - | - | - | - | $3,110 | - |
- - kWh |
- - kW-months/year |
- - Tgal |
$3,110 - gal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7121 UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT |
Savings: $2,912 Cost: $4,110 |
$2,912 | 29,606 | - | - | - | - | - | - |
$2,912 29,606 kWh |
- - kW-months/year |
- - Tgal |
- - gal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7492 USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE |
Savings: $2,195 Cost: $12,855 |
$2,195 | 84,413 | - | - | - | - | - | - |
$2,195 84,413 kWh |
- - kW-months/year |
- - Tgal |
- - gal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 3.5248 SEPARATE AND RECYCLE SCRAP METAL TO FOUNDRY OR FOR SALE |
Savings: $838 Cost: $624 |
- | - | - | - | $838 | - | - | - |
- - kWh |
- - kW-months/year |
$838 - Tgal |
- - gal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $470 Cost: $175 |
$470 | 18,068 | - | - | - | - | - | - |
$470 18,068 kWh |
- - kW-months/year |
- - Tgal |
- - gal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 3.1191 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS |
Savings: $288 Cost: - |
$288 | 3,902 | - | - | - | - | - | - |
$288 3,902 kWh |
- - kW-months/year |
- - Tgal |
- - gal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $22,446 Cost: $20,829 |
$7,331 | 192,369 | $7,895 | 180 | $4,110 | - | $3,110 | - | $7,331 192,369 kWh |
$7,895 180 kW-months/year |
$4,110 - Tgal |
$3,110 - gal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $13,397 Cost: $2,640 |
- | - | $6,177 | 42 | $4,110 | - | $3,110 | - | - - kWh |
$6,177 42 kW-months/year |
$4,110 - Tgal |
$3,110 - gal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | Tgal | $ | gal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Water Disposal | Other Liquid (non-haz) | Electricity Usage | Electricity Demand | Water Disposal | Other Liquid (non-haz) |