IAC Center | University of Wisconsin, Milwaukee |
---|---|
Assessment Year | 1991 |
Principal Product | HAND TOOLS |
NAICS | n/a |
SIC | 3423 - Hand And Edge Tools, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 150 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 3,000,000 Pieces |
Production Hrs. Annual | 4,000 |
Location (State) | IL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $231,616 | 2,985,053 | kWh | $0.08 |
Natural Gas | $134,835 | 34,895 | MMBtu | $3.86 |
TOTAL ENERGY COSTS | $366,451 | |||
RECOMMENDED SAVINGS* | $11,723 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4312 IMPROVE LUBRICATION PRACTICES |
Savings: $4,375 Cost: - |
$4,375 | 56,272 | - | - | - | - |
$4,375 56,272 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.3132 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS |
Savings: $2,019 Cost: - |
$2,019 | - | - | - | - | - |
$2,019 - kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7494 INSTALL STORM WINDOWS AND DOORS |
Savings: $2,291 Cost: $8,000 |
- | - | $2,291 | 594 | - | - |
- - kWh |
$2,291 594 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS |
Savings: $1,002 Cost: - |
$1,402 | - | - | - | $(-400) | - |
$1,402 - kWh |
- - MMBtu |
$(-400) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $601 Cost: $500 |
- | - | $601 | 156 | - | - |
- - kWh |
$601 156 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $19 Cost: $2,074 |
$155 | 2,052 | - | - | $(-136) | - |
$155 2,052 kWh |
- - MMBtu |
$(-136) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $91 Cost: $233 |
$91 | 1,172 | - | - | - | - |
$91 1,172 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,325 Cost: $3,660 |
$1,325 | 16,999 | - | - | - | - |
$1,325 16,999 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $11,723 Cost: $14,467 |
$9,367 | 76,495 | $2,892 | 750 | $(-536) | - | $9,367 76,495 kWh |
$2,892 750 MMBtu |
$(-536) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - - kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes |