IAC Assessment: WI0127
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: WI0127
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Wisconsin, Milwaukee
Assessment Year 1991
Principal Product MAYONNAISE,MARGARINE
NAICS n/a
SIC 2035 - Pickles, Sauces, And Salad Dressings
Sales $50,000,000-$100,000,000
# of Employees 400
Plant Area (Sq.Ft.) 0
Annual Production 218,800,000 Pounds
Production Hrs. Annual 6,000
Location (State) IL
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $1,099,310 18,055,686 kWh $0.06
Natural Gas $714,690 288,760 MMBtu $2.48
TOTAL ENERGY COSTS $1,814,000
RECOMMENDED SAVINGS* $963,403 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Natural Gas Electricity Usage Natural Gas
$ kWh $ MMBtu
01: 2.3191 USE DEMAND CONTROLLER OR LOAD SHEDDER Savings:
$20,052
Cost:
$15,000
$20,052 - - - $20,052
-
kWh
-
-
MMBtu
02: 2.2621 MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE Savings:
$12,150
Cost:
$7,000
$12,150 202,521 - - $12,150
202,521
kWh
-
-
MMBtu
03: 2.3132 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS Savings:
$8,373
Cost:
$16,000
$8,373 - - - $8,373
-
kWh
-
-
MMBtu
04: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$3,042
Cost:
$2,560
$3,042 46,893 - - $3,042
46,893
kWh
-
-
MMBtu
05: 2.7221 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA Savings:
$2,019
Cost:
-
$2,019 33,118 - - $2,019
33,118
kWh
-
-
MMBtu
06: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$140
Cost:
$276
$140 2,345 - - $140
2,345
kWh
-
-
MMBtu
07: 2.1131 REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC Savings:
$389
Cost:
$283
- - $389 157 -
-
kWh
$389
157
MMBtu
08: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS Savings:
$138
Cost:
$400
- - $138 56 -
-
kWh
$138
56
MMBtu
09: 2.3416 USE COMBINED CYCLE GAS TURBINE GENERATOR SETS WITH WASTE HEAT BOILERS CONNECTED TO TURBINE EXHAUST Savings:
$917,100
Cost:
-
$1,095,660 18,000,000 $(-178,560) (-72,000) $1,095,660
18,000,000
kWh
$(-178,560)
(-72,000)
MMBtu
TOTAL RECOMMENDED Savings:
$963,403
Cost:
$41,519
$1,141,436 18,284,877 $(-178,033) (-71,787) $1,141,436
18,284,877
kWh
$(-178,033)
(-71,787)
MMBtu
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - -
-
kWh
-
-
MMBtu
Savings
Cost
$ kWh $ MMBtu
Electricity Usage Natural Gas Electricity Usage Natural Gas