Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,077
matching recommendationsNAICS | 221 | Utilities |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LE0573 # 03 Y:2024 | 03 | 2024 | USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT | $361,764 | $1,321,539 | Implemented |
LE0573 # 05 Y:2024 | 05 | 2024 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $184,074 | $995,727 | Implemented |
LE0573 # 04 Y:2024 | 04 | 2024 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $1,318 | $5,952 | Implemented |
LE0573 # 02 Y:2024 | 02 | 2024 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $8,341 | $20,400 | Implemented |
LE0573 # 01 Y:2024 | 01 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,259 | $4,198 | Implemented |
UU0254 # 02 Y:2024 | 02 | 2024 | REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT | $9,712 | $81,738 | Implemented |
UU0254 # 06 Y:2024 | 06 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,182 | $5,868 | Implemented |
UU0254 # 03 Y:2024 | 03 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $509,495 | $6,000,000 | Implemented |
UU0254 # 04 Y:2024 | 04 | 2024 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $1,472 | $2,250 | Implemented |
UU0254 # 05 Y:2024 | 05 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $264 | $504 | Implemented |
UW2411 # 01 Y:2024 | 01 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $177 | $715 | Implemented |
UW2411 # 03 Y:2024 | 03 | 2024 | UPGRADE OBSOLETE EQUIPMENT | $2,275 | $0 | Implemented |
UW2411 # 02 Y:2024 | 02 | 2024 | REPLACE ELECTRIC MOTOR WITH FOSSIL FUEL ENGINE | $5,536 | $0 | Implemented |
SF0618 # 10 Y:2024 | 10 | 2024 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $875 | $3,607 | Implemented |
SF0618 # 04 Y:2024 | 04 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,266 | $3,170 | Implemented |
SF0618 # 01 Y:2024 | 01 | 2024 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,570 | $175 | Implemented |
SF0618 # 03 Y:2024 | 03 | 2024 | INSTALL EQUIPMENT TO UTILIZE WASTE FUEL | $705,605 | $250,000 | Implemented |
SF0618 # 05 Y:2024 | 05 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,359 | $2,340 | Implemented |
AS0576 # 06 Y:2024 | 06 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $872 | $1,035 | Implemented |
AS0576 # 01 Y:2024 | 01 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $188,394 | $1,306,404 | Implemented |
AS0576 # 08 Y:2024 | 08 | 2024 | INSTALL HEAT PIPES / RAISE COOLING SETPOINT | $138 | $90 | Implemented |
AS0576 # 07 Y:2024 | 07 | 2024 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $562 | $2,900 | Implemented |
AS0576 # 05 Y:2024 | 05 | 2024 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $886 | $700 | Implemented |
AS0576 # 03 Y:2024 | 03 | 2024 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $3,250 | $1,245 | Implemented |
WM0218 # 01 Y:2024 | 01 | 2024 | USE SYNTHETIC LUBRICANT | $16,984 | $11,275 | Implemented |