IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

2,275

matching recommendations
Reset
NAICS 221 Utilities
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OR0740 # 04 Y:2021 04 2021 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES $39,964 $60,439 Implemented
OR0740 # 05 Y:2021 05 2021 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $27,831 $84,560 Implemented
OR0740 # 06 Y:2021 06 2021 REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT $14,480 $12,929 Implemented
OR0740 # 07 Y:2021 07 2021 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $9,547 $3,289 Implemented
AM0808 # 01 Y:2020 01 2020 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS $89,600 $199,000 Not Implemented
AM0808 # 02 Y:2020 02 2020 ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM $10,942 $4,570 Implemented
AM0808 # 03 Y:2020 03 2020 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,862 $4,075 Implemented
AM0808 # 04 Y:2020 04 2020 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $100 $192 Implemented
SF0559 # 01 Y:2020 01 2020 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $2,636 $212 Implemented
SF0559 # 02 Y:2020 02 2020 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,557 $1,554 Implemented
SF0559 # 03 Y:2020 03 2020 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $26,836 $39,572 Implemented
SF0559 # 04 Y:2020 04 2020 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES $474 $1,290 Not Implemented
SF0559 # 05 Y:2020 05 2020 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $8,278 $23,119 Not Implemented
SF0559 # 06 Y:2020 06 2020 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES $13,782 $57,750 Not Implemented
OR0737 # 01 Y:2021 01 2021 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES $7,782 $0 Not Implemented
OR0737 # 02 Y:2021 02 2021 USE OPTIMUM SIZE AND CAPACITY EQUIPMENT $7,614 $0 Not Implemented
OR0737 # 03 Y:2021 03 2021 USE OPTIMUM SIZE AND CAPACITY EQUIPMENT $5,949 $0 Not Implemented
OR0737 # 04 Y:2021 04 2021 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $2,884 $0 Implemented
OR0737 # 05 Y:2021 05 2021 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES $3,820 $8,556 Implemented
CL2011 # 01 Y:2020 01 2020 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $4,964 $3,933 Implemented
CL2011 # 02 Y:2020 02 2020 INSTALL OCCUPANCY SENSORS $1,997 $295 Implemented
CL2011 # 03 Y:2020 03 2020 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $587 $0 Implemented
CL2011 # 04 Y:2020 04 2020 MODIFY FACILITY TO AVOID EXCESS MAINTENANCE COSTS $7,830 $4,500 Implemented
CL2011 # 05 Y:2020 05 2020 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $1,975 $400 Implemented
CL2010 # 01 Y:2020 01 2020 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $15,534 $13,514 Implemented