Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
253
matching recommendationsNAICS | 221 | Utilities |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SF0503 # 03 Y:2017 | 03 | 2017 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $802,468 | $1,600,000 | Implemented |
SF0503 # 02 Y:2017 | 02 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $123,711 | $243,952 | Implemented |
SF0503 # 01 Y:2017 | 01 | 2017 | USE OUTSIDE COLD WATER SOURCE AS A SUPPLY OF COOLING WATER | $8,497 | $7,120 | Implemented |
SF0496 # 01 Y:2017 | 01 | 2017 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $852 | $90 | Not Implemented |
SF0496 # 02 Y:2017 | 02 | 2017 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $1,991 | $546 | Implemented |
SF0496 # 03 Y:2017 | 03 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $22,454 | $23,168 | Implemented |
SF0496 # 04 Y:2017 | 04 | 2017 | INSTALL OCCUPANCY SENSORS | $1,681 | $3,001 | Implemented |
SF0496 # 05 Y:2017 | 05 | 2017 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $6,437 | $21,315 | Not Implemented |
SF0496 # 07 Y:2017 | 07 | 2017 | USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT | $169,204 | $790,554 | Not Implemented |
SF0496 # 06 Y:2017 | 06 | 2017 | REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT | $4,855 | $20,327 | Not Implemented |
SF0478 # 02 Y:2016 | 02 | 2016 | VENTILATION SYSTEM TO SHUT OFF WHEN ROOM IS NOT IN USE | $6,324 | $2,354 | Implemented |
SF0478 # 01 Y:2016 | 01 | 2016 | USE POWER DURING OFF-PEAK PERIODS | $5,976 | $0 | Implemented |
SF0478 # 03 Y:2016 | 03 | 2016 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $12,559 | $6,856 | Implemented |
SF0478 # 04 Y:2016 | 04 | 2016 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $3,956 | $2,003 | Not Implemented |
SF0478 # 05 Y:2016 | 05 | 2016 | INSTALL OCCUPANCY SENSORS | $18,801 | $20,415 | Implemented |
SF0478 # 06 Y:2016 | 06 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $25,062 | $48,543 | Implemented |
SF0478 # 07 Y:2016 | 07 | 2016 | USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT | $323,906 | $1,095,380 | Implemented |
SD0487 # 06 Y:2014 | 06 | 2014 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $2,473 | $2,350 | Implemented |
SD0487 # 01 Y:2014 | 01 | 2014 | USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT | $55,346 | $151,250 | Not Implemented |
SD0487 # 02 Y:2014 | 02 | 2014 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $13,532 | $99,966 | Implemented |
SD0487 # 03 Y:2014 | 03 | 2014 | UPGRADE OBSOLETE EQUIPMENT | $9,337 | $35,560 | Implemented |
SD0487 # 05 Y:2014 | 05 | 2014 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $3,282 | $9,400 | Implemented |
SD0487 # 04 Y:2014 | 04 | 2014 | REDUCE SCRAP PRODUCTION | $4,795 | $10,700 | Implemented |
SF0445 # 01 Y:2014 | 01 | 2014 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $8,564 | $0 | Implemented |
SF0445 # 02 Y:2014 | 02 | 2014 | TURN OFF EQUIPMENT WHEN NOT IN USE | $2,245 | $0 | Implemented |