Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
160
matching recommendationsNAICS | 2213 | Water, Sewage and Other Systems |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AS0503 # 07 Y:2021 | 07 | 2021 | INSTALL OCCUPANCY SENSORS | $9,147 | $2,290 | Implemented |
AS0503 # 06 Y:2021 | 06 | 2021 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $9,834 | $5,555 | Implemented |
AS0503 # 05 Y:2021 | 05 | 2021 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $25,372 | $918 | Implemented |
AS0503 # 04 Y:2021 | 04 | 2021 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $27,634 | $115 | Implemented |
AS0503 # 03 Y:2021 | 03 | 2021 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $35,467 | $918 | Implemented |
AS0503 # 02 Y:2021 | 02 | 2021 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $82,856 | $1,837 | Not Implemented |
AS0503 # 01 Y:2021 | 01 | 2021 | USE SOLAR HEAT TO MAKE ELECTRICTY | $316,547 | $4,413,360 | Implemented |
AS0501 # 01 Y:2021 | 01 | 2021 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $42,454 | $940 | Not Implemented |
AS0501 # 07 Y:2021 | 07 | 2021 | INSTALL OCCUPANCY SENSORS | $1,080 | $2,877 | Implemented |
AS0501 # 06 Y:2021 | 06 | 2021 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,736 | $1,408 | Not Implemented |
AS0501 # 05 Y:2021 | 05 | 2021 | INSTALL HEAT PIPES / RAISE COOLING SETPOINT | $1,787 | $103 | Not Implemented |
AS0501 # 04 Y:2021 | 04 | 2021 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $2,172 | $7,423 | Not Implemented |
AS0501 # 03 Y:2021 | 03 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,005 | $7,546 | Implemented |
AS0501 # 02 Y:2021 | 02 | 2021 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $36,391 | $37,849 | Not Implemented |
AS0500 # 05 Y:2021 | 05 | 2021 | INSTALL HEAT PIPES / RAISE COOLING SETPOINT | $718 | $38 | Implemented |
AS0500 # 04 Y:2021 | 04 | 2021 | INSTALL OCCUPANCY SENSORS | $1,279 | $1,850 | Implemented |
AS0500 # 03 Y:2021 | 03 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,453 | $8,113 | Implemented |
AS0500 # 02 Y:2021 | 02 | 2021 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $8,048 | $811 | Implemented |
AS0500 # 01 Y:2021 | 01 | 2021 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $231,021 | $2,706 | Not Implemented |
AS0496 # 02 Y:2021 | 02 | 2021 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $18,309 | $3,941 | Implemented |
AS0496 # 01 Y:2021 | 01 | 2021 | INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE | $174,284 | $89,232 | Not Implemented |
AS0496 # 03 Y:2021 | 03 | 2021 | TURN OFF EQUIPMENT WHEN NOT IN USE | $2,587 | $789 | Implemented |
AS0496 # 04 Y:2021 | 04 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,402 | $3,920 | Implemented |
AS0496 # 06 Y:2021 | 06 | 2021 | INSTALL HEAT PIPES / RAISE COOLING SETPOINT | $499 | $35 | Implemented |
AS0496 # 05 Y:2021 | 05 | 2021 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,262 | $6,259 | Implemented |