Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
4,132
matching recommendationsNAICS | 311 | Food Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AM0861 # 02 Y:2023 | 02 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $15,100 | $9,940 | Implemented |
AM0861 # 04 Y:2023 | 04 | 2023 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $3,960 | $460 | Implemented |
AM0861 # 05 Y:2023 | 05 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,870 | $13 | Implemented |
AM0861 # 06 Y:2023 | 06 | 2023 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $700 | $0 | Implemented |
LE0536 # 01 Y:2023 | 01 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,791 | $0 | Implemented |
LE0536 # 02 Y:2023 | 02 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,036 | $2,440 | Implemented |
LE0536 # 03 Y:2023 | 03 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $27,974 | $35,815 | Implemented |
LT8368 # 03 Y:2022 | 03 | 2022 | INSTALL OCCUPANCY SENSORS | $585 | $852 | Implemented |
SF0591 # 02 Y:2022 | 02 | 2022 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $9,922 | $0 | Implemented |
SF0591 # 03 Y:2022 | 03 | 2022 | REDUCE EXCESS STEAM BLEEDING | $9,616 | $0 | Implemented |
SF0591 # 04 Y:2022 | 04 | 2022 | REMOVE OR CLOSE OFF UNNEEDED COMPRESSED AIR LINES | $6,698 | $0 | Implemented |
SF0591 # 06 Y:2022 | 06 | 2022 | INSTALL SET-BACK TIMERS | $22,648 | $6,467 | Implemented |
SF0591 # 07 Y:2022 | 07 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $11,540 | $14,724 | Implemented |
SF0591 # 09 Y:2022 | 09 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $5,521 | $18,051 | Implemented |
UW2207 # 04 Y:2022 | 04 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,631 | $2,080 | Implemented |
UW2207 # 02 Y:2022 | 02 | 2022 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $685 | $112 | Implemented |
UW2207 # 01 Y:2022 | 01 | 2022 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,161 | $0 | Implemented |
UF0585 # 07 Y:2022 | 07 | 2022 | LEVEL ZERO – INSTALL CONTROL SYSTEMS FOR EXISTING EQUIPMENT | $19,210 | $10,000 | Implemented |
UF0585 # 06 Y:2022 | 06 | 2022 | LEVEL ONE – ADD COMMUNICATION USING IIOT DEVICES TO EXISTING CONTROL SYSTEM TO MODIFY OPERATIONS | $45,977 | $0 | Implemented |
UF0585 # 05 Y:2022 | 05 | 2022 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,345 | $0 | Implemented |
UF0585 # 04 Y:2022 | 04 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,918 | $756 | Implemented |
UF0585 # 03 Y:2022 | 03 | 2022 | INSTALL TURBULATORS | $6,811 | $7,500 | Implemented |
UF0585 # 02 Y:2022 | 02 | 2022 | INCREASE AMOUNT OF CONDENSATE RETURNED | $11,758 | $1,342 | Implemented |
UF0585 # 01 Y:2022 | 01 | 2022 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $21,858 | $44,939 | Implemented |
UW2205 # 01 Y:2022 | 01 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,244 | $12,938 | Implemented |