Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
4,132
matching recommendationsNAICS | 311 | Food Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
TA0050 # 02 Y:2003 | 02 | 2003 | RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | $47,100 | $5,202 | Implemented |
TA0050 # 03 Y:2003 | 03 | 2003 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $6,258 | $8,100 | Implemented |
TA0050 # 05 Y:2003 | 05 | 2003 | UPGRADE OBSOLETE EQUIPMENT | $5,795 | $11,200 | Implemented |
TA0050 # 07 Y:2003 | 07 | 2003 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,570 | $0 | Implemented |
TA0050 # 08 Y:2003 | 08 | 2003 | TURN OFF EQUIPMENT WHEN NOT IN USE | $1,676 | $0 | Implemented |
TA0050 # 10 Y:2003 | 10 | 2003 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $390 | $0 | Implemented |
OR0428 # 02 Y:2003 | 02 | 2003 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $307 | $0 | Implemented |
OR0428 # 03 Y:2003 | 03 | 2003 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $743 | $26 | Implemented |
OR0428 # 04 Y:2003 | 04 | 2003 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $437 | $500 | Implemented |
OR0428 # 07 Y:2003 | 07 | 2003 | RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS | $400 | $1,970 | Implemented |
WV0260 # 01 Y:2003 | 01 | 2003 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $876 | $130 | Implemented |
WV0260 # 04 Y:2003 | 04 | 2003 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $597 | $52 | Implemented |
WV0260 # 05 Y:2003 | 05 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,293 | $4,594 | Implemented |
WV0260 # 06 Y:2003 | 06 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $534 | $0 | Implemented |
WV0260 # 07 Y:2003 | 07 | 2003 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $1,720 | $400 | Implemented |
WV0260 # 08 Y:2003 | 08 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $175 | $0 | Implemented |
WV0260 # 09 Y:2003 | 09 | 2003 | USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY | $1,444 | $130 | Implemented |
WV0260 # 12 Y:2003 | 12 | 2003 | REPAIR AND ELIMINATE STEAM LEAKS | $411 | $1,000 | Implemented |
WV0260 # 13 Y:2003 | 13 | 2003 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $298 | $40 | Implemented |
SD0316 # 02 Y:2003 | 02 | 2003 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,922 | $0 | Implemented |
SD0316 # 03 Y:2003 | 03 | 2003 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,991 | $300 | Implemented |
GT0751 # 02 Y:2003 | 02 | 2003 | ADJUST BURNERS FOR EFFICIENT OPERATION | $31,370 | $5,000 | Implemented |
GT0751 # 03 Y:2003 | 03 | 2003 | TURN OFF EQUIPMENT WHEN NOT IN USE | $7,017 | $0 | Implemented |
GT0751 # 04 Y:2003 | 04 | 2003 | INSTALL OCCUPANCY SENSORS | $697 | $50 | Implemented |
GT0751 # 08 Y:2003 | 08 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,580 | $12,000 | Implemented |