Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
72
matching recommendationsNAICS | 311 | Food Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK1047 # 04 Y:2021 | 04 | 2021 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $876 | $500 | Implemented |
OK1047 # 02 Y:2021 | 02 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,774 | $6,045 | Implemented |
OK1047 # 01 Y:2021 | 01 | 2021 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $9,181 | $17,737 | Implemented |
OK1047 # 03 Y:2021 | 03 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,212 | $1,242 | Implemented |
OK1021 # 03 Y:2019 | 03 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,570 | $850 | Implemented |
OK1021 # 02 Y:2019 | 02 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,490 | $4,312 | Implemented |
OK1021 # 04 Y:2019 | 04 | 2019 | INSTALL / REPAIR INSULATION ON STEAM LINES | $6,865 | $426 | Implemented |
OK1021 # 01 Y:2019 | 01 | 2019 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $957 | $524 | Implemented |
OK1016 # 02 Y:2019 | 02 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,028 | $28,358 | Implemented |
OK1016 # 04 Y:2019 | 04 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $4,330 | $0 | Implemented |
OK1016 # 07 Y:2019 | 07 | 2019 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $485 | $636 | Implemented |
OK0937 # 05 Y:2016 | 05 | 2016 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $3,445 | $12,000 | Implemented |
OK0937 # 03 Y:2016 | 03 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,346 | $88,560 | Implemented |
OK0937 # 02 Y:2016 | 02 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,667 | $5,324 | Implemented |
OK0912 # 03 Y:2015 | 03 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $699 | $1,752 | Implemented |
OK0912 # 02 Y:2015 | 02 | 2015 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $2,191 | $8,250 | Implemented |
OK0912 # 06 Y:2015 | 06 | 2015 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $3,077 | $10,897 | Implemented |
OK0912 # 09 Y:2015 | 09 | 2015 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,274 | $460 | Implemented |
OK0912 # 01 Y:2015 | 01 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,007 | $1,150 | Implemented |
OK0912 # 08 Y:2015 | 08 | 2015 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $64 | $46 | Implemented |
OK0910 # 08 Y:2015 | 08 | 2015 | REPAIR AND ELIMINATE STEAM LEAKS | $18,886 | $375 | Implemented |
OK0910 # 03 Y:2015 | 03 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $25,309 | $1,250 | Implemented |
OK0910 # 05 Y:2015 | 05 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $70,459 | $247,939 | Implemented |
OK0910 # 07 Y:2015 | 07 | 2015 | INSTALL TIMERS AND/OR THERMOSTATS | $2,710 | $2,471 | Implemented |
OK0884 # 03 Y:2014 | 03 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,165 | $5,440 | Implemented |