Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
678
matching recommendationsNAICS | 31141 | Frozen Food Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK0695 # 02 Y:2004 | 02 | 2004 | RECOVER WASTE HEAT FROM EQUIPMENT | $17,436 | $17,500 | Not Implemented |
OK0695 # 01 Y:2004 | 01 | 2004 | CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD | $35,493 | $329,564 | Not Implemented |
OR0459 # 01 Y:2004 | 01 | 2004 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $4,500 | $10,500 | Not Implemented |
OR0459 # 02 Y:2004 | 02 | 2004 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $9,750 | $300 | Implemented |
OR0459 # 03 Y:2004 | 03 | 2004 | UPGRADE CONTROLS ON COMPRESSORS | $4,820 | $36,600 | Implemented |
OR0459 # 04 Y:2004 | 04 | 2004 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $34,250 | $2,000 | Implemented |
OR0459 # 05 Y:2004 | 05 | 2004 | ESTABLISH BURNER MAINTENANCE SCHEDULE FOR BOILERS | $5,330 | $2,825 | Implemented |
OR0459 # 06 Y:2004 | 06 | 2004 | OPTIMIZE PLANT POWER FACTOR | $2,730 | $5,130 | Implemented |
OR0457 # 01 Y:2004 | 01 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $24,600 | $25,000 | Implemented |
OR0457 # 02 Y:2004 | 02 | 2004 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $6,140 | $10,000 | Not Implemented |
OR0457 # 03 Y:2004 | 03 | 2004 | UPGRADE CONTROLS ON COMPRESSORS | $31,300 | $0 | Implemented |
OR0457 # 04 Y:2004 | 04 | 2004 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $13,100 | $42,000 | Not Implemented |
OR0457 # 05 Y:2004 | 05 | 2004 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $18,900 | $0 | Implemented |
OR0457 # 06 Y:2004 | 06 | 2004 | ESTABLISH BURNER MAINTENANCE SCHEDULE FOR BOILERS | $2,520 | $300 | Implemented |
IC0079 # 01 Y:2004 | 01 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $522 | $400 | Implemented |
IC0079 # 02 Y:2004 | 02 | 2004 | USE OPTIMUM TEMPERATURE | $4,226 | $0 | Not Implemented |
IC0079 # 03 Y:2004 | 03 | 2004 | INSTALL AUTOMATIC STACK DAMPER | $943 | $375 | Not Implemented |
IC0079 # 04 Y:2004 | 04 | 2004 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $311 | $224 | Implemented |
IC0079 # 05 Y:2004 | 05 | 2004 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $5,244 | $18,858 | Implemented |
IC0079 # 06 Y:2004 | 06 | 2004 | INSTALL OCCUPANCY SENSORS | $2,248 | $9,540 | Implemented |
IC0079 # 07 Y:2004 | 07 | 2004 | ADJUST / MAINTAIN FORK LIFT TRUCKS FOR MOST EFFICIENT OPERATION | $1,706 | $0 | Not Implemented |
IC0079 # 08 Y:2004 | 08 | 2004 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $2,734 | $0 | Implemented |
IC0079 # 09 Y:2004 | 09 | 2004 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $1,159,243 | $6,681,290 | Implemented |
WV0296 # 01 Y:2004 | 01 | 2004 | BURN A LESS EXPENSIVE GRADE OF FUEL | $70,180 | $130 | Not Implemented |
WV0296 # 02 Y:2004 | 02 | 2004 | RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER | $15,329 | $10,875 | Not Implemented |