Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
19
matching recommendationsNAICS | 3115 | Dairy Product Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UD1014 # 05 Y:2020 | 05 | 2020 | INSULATE BARE EQUIPMENT | $28,500 | $18,326 | Implemented |
UD0995 # 09 Y:2019 | 09 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,887 | $17,856 | Implemented |
UD0995 # 02 Y:2019 | 02 | 2019 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,443 | $1,500 | Implemented |
UD0995 # 03 Y:2019 | 03 | 2019 | REPAIR OR REPLACE STEAM TRAPS | $5,974 | $1,800 | Implemented |
UD0995 # 04 Y:2019 | 04 | 2019 | OPTIMIZE PLANT POWER FACTOR | $1,159 | $3,500 | Implemented |
UD0995 # 07 Y:2019 | 07 | 2019 | INSTALL / REPAIR INSULATION ON STEAM LINES | $5,847 | $11,694 | Implemented |
UD0995 # 08 Y:2019 | 08 | 2019 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $606 | $0 | Implemented |
UD0938 # 06 Y:2015 | 06 | 2015 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,415 | $0 | Implemented |
UD0938 # 07 Y:2015 | 07 | 2015 | DEVELOP A REPAIR/REPLACE POLICY | $152 | $530 | Implemented |
UD0938 # 02 Y:2015 | 02 | 2015 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $3,298 | $0 | Implemented |
WV0502 # 01 Y:2015 | 01 | 2015 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $13,685 | $1,000 | Implemented |
WV0502 # 02 Y:2015 | 02 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $13,334 | $25,930 | Implemented |
WV0502 # 03 Y:2015 | 03 | 2015 | USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY | $12,681 | $18,000 | Implemented |
WV0502 # 07 Y:2015 | 07 | 2015 | DEVELOP A REPAIR/REPLACE POLICY | $3,350 | $724 | Implemented |
WV0502 # 08 Y:2015 | 08 | 2015 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,826 | $500 | Implemented |
WV0502 # 09 Y:2015 | 09 | 2015 | INSULATE BARE EQUIPMENT | $812 | $2,934 | Implemented |
WV0502 # 10 Y:2015 | 10 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $321 | $854 | Implemented |
UM0272 # 01 Y:2005 | 01 | 2005 | RECOVER WASTE HEAT FROM EQUIPMENT | $2,828 | $1,000 | Implemented |
UM0272 # 03 Y:2005 | 03 | 2005 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $2,631 | $300 | Implemented |