Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
138
matching recommendationsNAICS | 311615 | Poultry Processing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AM0513 # 09 Y:2006 | 09 | 2006 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $2,170 | $144 | Implemented |
AM0513 # 10 Y:2006 | 10 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,415 | $690 | Implemented |
LL0255 # 06 Y:2006 | 06 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,638 | $1,520 | Implemented |
LL0255 # 07 Y:2006 | 07 | 2006 | INSTALL OCCUPANCY SENSORS | $3,853 | $1,320 | Implemented |
LL0255 # 08 Y:2006 | 08 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $844 | $700 | Implemented |
LL0255 # 09 Y:2006 | 09 | 2006 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $747 | $69 | Implemented |
LL0255 # 10 Y:2006 | 10 | 2006 | USE PHOTOCELL CONTROLS | $244 | $30 | Implemented |
IC0115 # 01 Y:2006 | 01 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,445 | $26,134 | Implemented |
IC0115 # 02 Y:2006 | 02 | 2006 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $3,985 | $16,831 | Implemented |
IC0115 # 03 Y:2006 | 03 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $11,680 | $65,036 | Implemented |
IC0115 # 04 Y:2006 | 04 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $272 | $420 | Implemented |
IC0115 # 06 Y:2006 | 06 | 2006 | INSTALL DIRECT ACTING UNITS IN PLACE OF COMPRESSED AIR PRESSURE SYSTEM IN SAFETY SYSTEM | $54 | $284 | Implemented |
IC0115 # 08 Y:2006 | 08 | 2006 | REPLACE BOILER | $125,042 | $193,200 | Implemented |
IC0115 # 09 Y:2006 | 09 | 2006 | REDUCE EXCESS STEAM BLEEDING | $29,262 | $5,000 | Implemented |
SF0308 # 01 Y:2005 | 01 | 2005 | REPAIR AND ELIMINATE STEAM LEAKS | $1,671 | $0 | Implemented |
SF0308 # 04 Y:2005 | 04 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,813 | $1,512 | Implemented |
SF0308 # 06 Y:2005 | 06 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,381 | $9,206 | Implemented |
SF0308 # 07 Y:2005 | 07 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $455 | $1,925 | Implemented |
OK0670 # 02 Y:2003 | 02 | 2003 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $4,120 | $0 | Implemented |
OK0670 # 03 Y:2003 | 03 | 2003 | CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE | $12,292 | $0 | Implemented |
SU0164 # 02 Y:2003 | 02 | 2003 | USE OPTIMUM THICKNESS INSULATION | $115,419 | $348,540 | Implemented |
SU0164 # 04 Y:2003 | 04 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $13,096 | $55,580 | Implemented |
SU0164 # 05 Y:2003 | 05 | 2003 | REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED | $8,721 | $0 | Implemented |
SU0164 # 07 Y:2003 | 07 | 2003 | REDESIGN PROCESS | $6,861 | $270 | Implemented |
SU0164 # 08 Y:2003 | 08 | 2003 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $3,485 | $700 | Implemented |