Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
23
matching recommendationsNAICS | 3118 | Bakeries and Tortilla Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MZ0277 # 09 Y:2019 | 09 | 2019 | REPAIR FURNACES AND OVEN DOORS SO THAT THEY SEAL EFFICIENTLY | $409 | $1,200 | Implemented |
MZ0277 # 08 Y:2019 | 08 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,816 | $3,021 | Implemented |
MZ0277 # 07 Y:2019 | 07 | 2019 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $70,665 | $233,814 | Implemented |
MZ0277 # 06 Y:2019 | 06 | 2019 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $55,889 | $160 | Implemented |
MZ0277 # 04 Y:2019 | 04 | 2019 | INSTALL OCCUPANCY SENSORS | $1,650 | $2,700 | Implemented |
MZ0277 # 03 Y:2019 | 03 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,416 | $4,211 | Implemented |
IA0532 # 02 Y:2015 | 02 | 2015 | RECOVER WASTE HEAT FROM EQUIPMENT | $5,883 | $2,175 | Implemented |
IA0532 # 08 Y:2015 | 08 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $664 | $1,752 | Implemented |
IA0532 # 07 Y:2015 | 07 | 2015 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $893 | $35 | Implemented |
IA0532 # 05 Y:2015 | 05 | 2015 | DIRECT WARMEST AIR TO COMBUSTION INTAKE | $1,465 | $210 | Implemented |
IA0532 # 04 Y:2015 | 04 | 2015 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $5,935 | $9,474 | Implemented |
IA0532 # 01 Y:2015 | 01 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,363 | $44,410 | Implemented |
IA0495 # 01 Y:2013 | 01 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,154 | $13,790 | Implemented |
IA0495 # 02 Y:2013 | 02 | 2013 | INSTALL OCCUPANCY SENSORS | $189 | $612 | Implemented |
IA0495 # 03 Y:2013 | 03 | 2013 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $1,071 | $741 | Implemented |
IA0495 # 05 Y:2013 | 05 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $853 | $500 | Implemented |
IA0495 # 06 Y:2013 | 06 | 2013 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $106 | $35 | Implemented |
IA0495 # 07 Y:2013 | 07 | 2013 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $2,715 | $11,000 | Implemented |
IA0403 # 03 Y:2007 | 03 | 2007 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,132 | $25 | Implemented |
IA0403 # 04 Y:2007 | 04 | 2007 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $855 | $400 | Implemented |
IA0403 # 05 Y:2007 | 05 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,814 | $12,468 | Implemented |
IA0403 # 06 Y:2007 | 06 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,368 | $14,768 | Implemented |
IA0403 # 01 Y:2007 | 01 | 2007 | RECOVER WASTE HEAT FROM EQUIPMENT | $984 | $750 | Implemented |