Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
82
matching recommendationsNAICS | 311824 | Dry Pasta, Dough, and Flour Mixes Manufacturing from Purchased Flour |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
CM1016 # 01 Y:2023 | 01 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $2,957 | $0 | n/a |
BS0124 # 02 Y:2019 | 02 | 2019 | INSTALL / REPAIR INSULATION ON STEAM LINES | $392 | $1,259 | Not Implemented |
BS0124 # 01 Y:2019 | 01 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,766 | $6,213 | Not Implemented |
BS0124 # 03 Y:2019 | 03 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,609 | $1,030 | Not Implemented |
BS0124 # 04 Y:2019 | 04 | 2019 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $16,460 | $2,200 | Not Implemented |
IA0495 # 06 Y:2013 | 06 | 2013 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $106 | $35 | Implemented |
IA0495 # 01 Y:2013 | 01 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,154 | $13,790 | Implemented |
IA0495 # 02 Y:2013 | 02 | 2013 | INSTALL OCCUPANCY SENSORS | $189 | $612 | Implemented |
IA0495 # 03 Y:2013 | 03 | 2013 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $1,071 | $741 | Implemented |
IA0495 # 04 Y:2013 | 04 | 2013 | DIRECT WARMEST AIR TO COMBUSTION INTAKE | $623 | $350 | Not Implemented |
IA0495 # 05 Y:2013 | 05 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $853 | $500 | Implemented |
IA0495 # 07 Y:2013 | 07 | 2013 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $2,715 | $11,000 | Implemented |
SD0432 # 07 Y:2011 | 07 | 2011 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,373 | $8,285 | Not Implemented |
SD0432 # 06 Y:2011 | 06 | 2011 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $3,408 | $8,000 | Not Implemented |
SD0432 # 05 Y:2011 | 05 | 2011 | INSTALL OCCUPANCY SENSORS | $204 | $427 | Implemented |
SD0432 # 04 Y:2011 | 04 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,412 | $800 | Not Implemented |
SD0432 # 03 Y:2011 | 03 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $214 | $100 | Not Implemented |
SD0432 # 02 Y:2011 | 02 | 2011 | USE INSULATION IN FURNACES TO FACILITATE HEATING / COOLING | $2,059 | $800 | Implemented |
SD0432 # 01 Y:2011 | 01 | 2011 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $1,239 | $0 | Implemented |
UM0312 # 10 Y:2006 | 10 | 2006 | INSTALL OCCUPANCY SENSORS | $508 | $276 | Not Implemented |
UM0312 # 09 Y:2006 | 09 | 2006 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $857 | $300 | Not Implemented |
UM0312 # 04 Y:2006 | 04 | 2006 | TURN OFF EQUIPMENT WHEN NOT IN USE | $6,421 | $100 | Not Implemented |
UM0312 # 03 Y:2006 | 03 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,355 | $15,984 | Not Implemented |
UM0312 # 02 Y:2006 | 02 | 2006 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $14,289 | $4,200 | Not Implemented |
UM0312 # 01 Y:2006 | 01 | 2006 | TURN OFF EQUIPMENT WHEN NOT IN USE | $15,410 | $500 | Not Implemented |