Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,548
matching recommendationsNAICS | 3219 | Other Wood Product Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AS0364 # 01 Y:2003 | 01 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,347 | $7,928 | Not Implemented |
AS0364 # 02 Y:2003 | 02 | 2003 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $221 | $524 | Not Implemented |
AS0364 # 03 Y:2003 | 03 | 2003 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $990 | $150 | Not Implemented |
AS0364 # 04 Y:2003 | 04 | 2003 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $9,291 | $31,527 | Not Implemented |
AS0364 # 05 Y:2003 | 05 | 2003 | REDUCE VENTILATION AIR | $285 | $10 | Not Implemented |
UF0331 # 01 Y:2003 | 01 | 2003 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $6,357 | $18,567 | Implemented |
UF0331 # 02 Y:2003 | 02 | 2003 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $3,423 | $0 | Implemented |
UF0331 # 03 Y:2003 | 03 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,837 | $11,405 | Implemented |
UF0331 # 04 Y:2003 | 04 | 2003 | ADD AREA LIGHTING SWITCHES | $924 | $1,649 | Implemented |
UF0331 # 05 Y:2003 | 05 | 2003 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $7,190 | $32,481 | Implemented |
UF0331 # 06 Y:2003 | 06 | 2003 | RECYCLE AIR FOR HEATING, VENTILATION AND AIR CONDITIONING | $14,275 | $55,800 | Not Implemented |
UF0331 # 07 Y:2003 | 07 | 2003 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $907 | $0 | Implemented |
UF0331 # 08 Y:2003 | 08 | 2003 | TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY | $7,000 | $3,000 | Implemented |
UF0331 # 09 Y:2003 | 09 | 2003 | MOVE PRODUCT USING MECHANICAL MEANS | $2,340 | $2,372 | Implemented |
AM0444 # 01 Y:2003 | 01 | 2003 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $11,800 | $0 | Implemented |
AM0444 # 02 Y:2003 | 02 | 2003 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $460 | $200 | Implemented |
AM0444 # 03 Y:2003 | 03 | 2003 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $390 | $80 | Implemented |
AM0444 # 04 Y:2003 | 04 | 2003 | USE SYNTHETIC LUBRICANT | $280 | $0 | Not Implemented |
AM0444 # 05 Y:2003 | 05 | 2003 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $3,950 | $10,000 | Not Implemented |
IA0324 # 01 Y:2003 | 01 | 2003 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,364 | $157 | Implemented |
IA0324 # 02 Y:2003 | 02 | 2003 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $936 | $446 | Not Implemented |
IA0324 # 03 Y:2003 | 03 | 2003 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $572 | $712 | Not Implemented |
IA0324 # 04 Y:2003 | 04 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $632 | $124 | Implemented |
IA0324 # 05 Y:2003 | 05 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,661 | $6,189 | Not Implemented |
IA0324 # 06 Y:2003 | 06 | 2003 | OPTIMIZE PLANT POWER FACTOR | $11,651 | $20,000 | Not Implemented |