Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
59
matching recommendationsNAICS | 32191 | Millwork |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UA0176 # 04 Y:2017 | 04 | 2017 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $21,678 | $38,382 | Not Implemented |
UA0176 # 07 Y:2017 | 07 | 2017 | MODIFY STARTUP/SHUTDOWN TIMES | $1,804 | $0 | Not Implemented |
UA0176 # 05 Y:2017 | 05 | 2017 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $9,273 | $2,645 | Implemented |
UA0127 # 09 Y:2014 | 09 | 2014 | INSTALL / REPAIR INSULATION ON STEAM LINES | $220 | $790 | Implemented |
UA0127 # 08 Y:2014 | 08 | 2014 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $9,469 | $40,000 | Implemented |
UA0127 # 07 Y:2014 | 07 | 2014 | USE PHOTOCELL CONTROLS | $156 | $116 | Not Implemented |
UA0127 # 06 Y:2014 | 06 | 2014 | INSTALL OCCUPANCY SENSORS | $1,431 | $95 | Not Implemented |
UA0127 # 05 Y:2014 | 05 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,037 | $28,162 | Not Implemented |
UA0127 # 04 Y:2014 | 04 | 2014 | MODIFY STARTUP/SHUTDOWN TIMES | $11,493 | $0 | Not Implemented |
UA0127 # 03 Y:2014 | 03 | 2014 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,280 | $1,500 | Implemented |
UA0127 # 02 Y:2014 | 02 | 2014 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,739 | $6,195 | Implemented |
UA0127 # 01 Y:2014 | 01 | 2014 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $8,119 | $9,967 | Not Implemented |
UA3028 # 01 Y:2013 | 01 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $22,215 | $5,595 | Implemented |
UA3028 # 04 Y:2013 | 04 | 2013 | IMPROVE COMBUSTION CONTROL CAPABILITY | $16,926 | $2,300 | Not Implemented |
UA3028 # 02 Y:2013 | 02 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,021 | $6,562 | Not Implemented |
UA3028 # 03 Y:2013 | 03 | 2013 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,307 | $1,000 | Not Implemented |
UA0038 # 10 Y:2009 | 10 | 2009 | INSTALL / REPAIR INSULATION ON STEAM LINES | $1,021 | $1,018 | Not Implemented |
UA0038 # 09 Y:2009 | 09 | 2009 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $5,636 | $17,820 | Not Implemented |
UA0038 # 08 Y:2009 | 08 | 2009 | INSTALL TIMERS AND/OR THERMOSTATS | $1,109 | $850 | Implemented |
UA0038 # 07 Y:2009 | 07 | 2009 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $458 | $1,858 | Implemented |
UA0038 # 06 Y:2009 | 06 | 2009 | USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER | $1,493 | $6,000 | Not Implemented |
UA0038 # 05 Y:2009 | 05 | 2009 | USE PHOTOCELL CONTROLS | $1,324 | $1,394 | Implemented |
UA0038 # 04 Y:2009 | 04 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $27,302 | $58,596 | Not Implemented |
UA0038 # 03 Y:2009 | 03 | 2009 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $263 | $0 | Implemented |
UA0038 # 02 Y:2009 | 02 | 2009 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $9,713 | $3,000 | Implemented |