Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
32
matching recommendationsNAICS | 32191 | Millwork |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UW2408 # 08 Y:2024 | 08 | 2024 | INSULATE FEEDWATER TANK | $2,901 | $290 | n/a |
UW2408 # 10 Y:2024 | 10 | 2024 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $145,176 | $144,799 | n/a |
UW2408 # 09 Y:2024 | 09 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $61,411 | $421,830 | n/a |
UW2408 # 07 Y:2024 | 07 | 2024 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $34,834 | $133,560 | n/a |
UW2408 # 06 Y:2024 | 06 | 2024 | RECYCLE AIR FOR HEATING, VENTILATION AND AIR CONDITIONING | $35,732 | $2,619 | n/a |
UW2408 # 05 Y:2024 | 05 | 2024 | OPTIMIZE PLANT POWER FACTOR | $45,697 | $89,919 | n/a |
UW2408 # 04 Y:2024 | 04 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $32,306 | $2,080 | n/a |
UW2408 # 03 Y:2024 | 03 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $8,014 | $0 | n/a |
UW2408 # 02 Y:2024 | 02 | 2024 | INSTALL / REPAIR INSULATION ON STEAM LINES | $116,105 | $13,500 | n/a |
UW2408 # 01 Y:2024 | 01 | 2024 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $13,069 | $103,000 | n/a |
OR0686 # 06 Y:2017 | 06 | 2017 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $5,743 | $500 | Not Implemented |
OR0686 # 05 Y:2017 | 05 | 2017 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $15,115 | $16,115 | Not Implemented |
OR0686 # 04 Y:2017 | 04 | 2017 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,155 | $0 | Not Implemented |
OR0686 # 03 Y:2017 | 03 | 2017 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $15,997 | $1,200 | Not Implemented |
OR0686 # 02 Y:2017 | 02 | 2017 | TURN OFF EQUIPMENT WHEN NOT IN USE | $5,219 | $0 | Not Implemented |
OR0686 # 01 Y:2017 | 01 | 2017 | DEVELOP STANDARD OPERATING PROCEDURES | $181,947 | $31,400 | Not Implemented |
BS0084 # 03 Y:2016 | 03 | 2016 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $4,738 | $825 | Not Implemented |
BS0084 # 05 Y:2016 | 05 | 2016 | INSULATE BARE EQUIPMENT | $118 | $264 | Not Implemented |
BS0084 # 04 Y:2016 | 04 | 2016 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $751 | $243 | Not Implemented |
BS0084 # 01 Y:2016 | 01 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $31,444 | $31,350 | Not Implemented |
BS0084 # 02 Y:2016 | 02 | 2016 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $3,854 | $15 | Not Implemented |
BS0058 # 01 Y:2015 | 01 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,953 | $9,195 | Not Implemented |
BS0058 # 02 Y:2015 | 02 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,672 | $422 | Not Implemented |
BS0058 # 04 Y:2015 | 04 | 2015 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $273 | $739 | Not Implemented |
BS0058 # 05 Y:2015 | 05 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,259 | $18,330 | Not Implemented |