IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

300

matching recommendations
Reset
NAICS 324122 Asphalt Shingle and Coating Materials Manufacturing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
DL0152 # 05 Y:2015 05 2015 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $8,400 $46,500 Not Implemented
DL0152 # 06 Y:2015 06 2015 UTILIZE A LESS EXPENSIVE COOLING METHOD $13,980 $92,000 Not Implemented
DL0152 # 07 Y:2015 07 2015 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $57,540 $1,325,000 Implemented
OK0919 # 03 Y:2015 03 2015 INSTALL OCCUPANCY SENSORS $815 $3,390 Implemented
OK0919 # 02 Y:2015 02 2015 USE PHOTOCELL CONTROLS $2,030 $1,790 Not Implemented
OK0919 # 01 Y:2015 01 2015 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $758 $1,688 Implemented
OK0919 # 04 Y:2015 04 2015 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $4,498 $3,000 Implemented
OK0919 # 05 Y:2015 05 2015 REPLACE BOILER $10,468 $22,000 Not Implemented
OK0919 # 06 Y:2015 06 2015 REPAIR AND ELIMINATE STEAM LEAKS $435 $600 Implemented
OK0919 # 07 Y:2015 07 2015 RECOVER WASTE HEAT FROM EQUIPMENT $4,213 $6,000 Not Implemented
OK0919 # 08 Y:2015 08 2015 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $2,725 $2,000 Implemented
OK0919 # 09 Y:2015 09 2015 INSTALL / REPAIR INSULATION ON STEAM LINES $3,124 $5,120 Implemented
OK0919 # 10 Y:2015 10 2015 INSTALL SET-BACK TIMERS $1,991 $100 Implemented
OK0919 # 11 Y:2015 11 2015 TURN OFF EQUIPMENT WHEN NOT IN USE $208 $210 Not Implemented
CO0701 # 04 Y:2015 04 2015 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,230 $2,460 Implemented
CO0701 # 03 Y:2015 03 2015 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $3,920 $3,750 Implemented
CO0701 # 02 Y:2015 02 2015 INSULATE BARE EQUIPMENT $19,610 $20,000 Implemented
CO0701 # 01 Y:2015 01 2015 USE WASTE HEAT WITH A CLOSED-CYCLE GAS TURBINE-GENERATOR SET TO COGENERATE ELECTRICITY AND HEAT $32,810 $82,650 Not Implemented
OR0642 # 07 Y:2015 07 2015 INSULATE BARE EQUIPMENT $898 $2,015 Implemented
OR0642 # 05 Y:2015 05 2015 ADJUST BURNERS FOR EFFICIENT OPERATION $1,833 $500 Implemented
OR0642 # 04 Y:2015 04 2015 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS $5,825 $22,383 Not Implemented
OR0642 # 03 Y:2015 03 2015 ADJUST / MAINTAIN FORK LIFT TRUCKS FOR MOST EFFICIENT OPERATION $46,293 $100,000 Not Implemented
OR0642 # 01 Y:2015 01 2015 MODIFY STARTUP/SHUTDOWN TIMES $6,091 $44,052 Implemented
OR0642 # 02 Y:2015 02 2015 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $16,013 $24,232 Implemented
OR0642 # 06 Y:2015 06 2015 USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL $64,347 $61,077 Not Implemented