Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
995
matching recommendationsNAICS | 3251 | Basic Chemical Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UM0332 # 07 Y:2007 | 07 | 2007 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $1,180 | $1,540 | Not Implemented |
IA0410 # 01 Y:2007 | 01 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,031 | $13,186 | Implemented |
IA0410 # 02 Y:2007 | 02 | 2007 | INSTALL OCCUPANCY SENSORS | $799 | $1,078 | Implemented |
IA0410 # 03 Y:2007 | 03 | 2007 | PREHEAT COMBUSTION AIR WITH WASTE HEAT | $1,146 | $2,400 | Implemented |
IA0410 # 04 Y:2007 | 04 | 2007 | REPAIR AND ELIMINATE STEAM LEAKS | $4,767 | $1,200 | Implemented |
IA0410 # 05 Y:2007 | 05 | 2007 | INSTALL / REPAIR INSULATION ON STEAM LINES | $10,352 | $3,350 | Implemented |
IA0410 # 06 Y:2007 | 06 | 2007 | INSULATE BARE EQUIPMENT | $7,135 | $2,000 | Implemented |
IA0410 # 07 Y:2007 | 07 | 2007 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $93 | $38 | Implemented |
IA0410 # 08 Y:2007 | 08 | 2007 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,443 | $215 | Implemented |
IA0410 # 09 Y:2007 | 09 | 2007 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,380 | $280 | Implemented |
OK0749 # 01 Y:2007 | 01 | 2007 | MINIMIZE BOILER BLOWDOWN WITH BETTER FEEDWATER TREATMENT | $74,106 | $206,725 | Not Implemented |
OK0749 # 02 Y:2007 | 02 | 2007 | REDUCE EXCESSIVE BOILER BLOWDOWN | $66,275 | $21,000 | Not Implemented |
OK0749 # 03 Y:2007 | 03 | 2007 | INSTALL / REPAIR INSULATION ON STEAM LINES | $126,819 | $38,280 | Not Implemented |
OK0749 # 04 Y:2007 | 04 | 2007 | REPAIR AND ELIMINATE STEAM LEAKS | $93,609 | $4,680 | Not Implemented |
OK0749 # 05 Y:2007 | 05 | 2007 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $3,286 | $1,985 | Not Implemented |
OK0749 # 06 Y:2007 | 06 | 2007 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $5,461 | $0 | Implemented |
OK0749 # 07 Y:2007 | 07 | 2007 | INCREASE AMOUNT OF CONDENSATE RETURNED | $181,080 | $110,352 | Not Implemented |
OK0749 # 08 Y:2007 | 08 | 2007 | OPERATE BOILERS ON HIGH FIRE SETTING | $238,762 | $50,000 | Not Implemented |
NC0350 # 01 Y:2006 | 01 | 2006 | RECOVER WASTE HEAT FROM EQUIPMENT | $122,745 | $114,000 | Not Implemented |
NC0350 # 02 Y:2006 | 02 | 2006 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $13,138 | $10,500 | Not Implemented |
NC0350 # 03 Y:2006 | 03 | 2006 | USE OPTIMUM THICKNESS INSULATION | $12,275 | $1,000 | Implemented |
NC0350 # 04 Y:2006 | 04 | 2006 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $15,381 | $2,000 | Not Implemented |
NC0350 # 05 Y:2006 | 05 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $330 | $100 | Implemented |
NC0348 # 01 Y:2006 | 01 | 2006 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $98,735 | $59,350 | Not Implemented |
NC0348 # 02 Y:2006 | 02 | 2006 | CLEAN CONDENSER TUBES | $123,800 | $5,000 | Not Implemented |