Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
84
matching recommendationsNAICS | 3252 | Resin, Synthetic Rubber, and Artificial Synthetic Fibers and Filaments Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MS0360 # 03 Y:2010 | 03 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,606 | $18,481 | Not Implemented |
MS0360 # 02 Y:2010 | 02 | 2010 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $91,795 | $240,500 | Implemented |
MS0360 # 01 Y:2010 | 01 | 2010 | RECOVER WASTE HEAT FROM EQUIPMENT | $244,785 | $930,000 | Not Implemented |
AM0587 # 02 Y:2010 | 02 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,460 | $21,600 | Implemented |
AM0587 # 01 Y:2010 | 01 | 2010 | REPAIR AND ELIMINATE STEAM LEAKS | $8,000 | $5,000 | Implemented |
AM0587 # 09 Y:2010 | 09 | 2010 | USE SYNTHETIC LUBRICANT | $980 | $0 | Not Implemented |
AM0587 # 08 Y:2010 | 08 | 2010 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $1,521 | $560 | Implemented |
AM0587 # 07 Y:2010 | 07 | 2010 | INSTALL SKYLIGHTS | $2,550 | $2,030 | Not Implemented |
AM0587 # 06 Y:2010 | 06 | 2010 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $3,250 | $500 | Implemented |
AM0587 # 05 Y:2010 | 05 | 2010 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $4,760 | $42 | Not Implemented |
AM0587 # 04 Y:2010 | 04 | 2010 | OPTIMIZE PLANT POWER FACTOR | $5,087 | $21,130 | Not Implemented |
AM0587 # 03 Y:2010 | 03 | 2010 | INSTALL / REPAIR INSULATION ON STEAM LINES | $5,760 | $1,030 | Implemented |
MS0362 # 01 Y:2010 | 01 | 2010 | INSTALL SMALLER BOILER (INCREASE HIGH FIRE DUTY CYCLE) | $129,172 | $586,857 | Implemented |
NC0406 # 10 Y:2010 | 10 | 2010 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $276,388 | $214,700 | Implemented |
NC0406 # 08 Y:2010 | 08 | 2010 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $508 | $920 | Implemented |
NC0406 # 06 Y:2010 | 06 | 2010 | RECOVER WASTE HEAT FROM EQUIPMENT | $10,210 | $15,045 | Not Implemented |
NC0406 # 01 Y:2010 | 01 | 2010 | ADOPT IN-HOUSE MATERIAL GENERATION | $77,083 | $85,000 | Not Implemented |
NC0406 # 11 Y:2010 | 11 | 2010 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $20,625 | $50,000 | Implemented |
NC0406 # 09 Y:2010 | 09 | 2010 | INSTALL OCCUPANCY SENSORS | $1,958 | $3,256 | Implemented |
NC0406 # 02 Y:2010 | 02 | 2010 | TREAT AND REUSE RINSE WATERS | $51,487 | $8,875 | Not Implemented |
NC0406 # 04 Y:2010 | 04 | 2010 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $16,743 | $50,000 | Implemented |
NC0406 # 05 Y:2010 | 05 | 2010 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,835 | $100 | Implemented |
NC0406 # 03 Y:2010 | 03 | 2010 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $11,177 | $50 | Implemented |
NC0406 # 07 Y:2010 | 07 | 2010 | USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER | $4,747 | $8,000 | Not Implemented |
MZ0047 # 03 Y:2010 | 03 | 2010 | USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER | $5,857 | $80,000 | Not Implemented |