Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
173
matching recommendationsNAICS | 32561 | Soap and Cleaning Compound Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LS2414 # 04 Y:2024 | 04 | 2024 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $810,158 | $2,364,120 | Implemented |
LS2414 # 02 Y:2024 | 02 | 2024 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $265,645 | $63,000 | Implemented |
IC0279 # 02 Y:2023 | 02 | 2023 | INSULATE BARE EQUIPMENT | $2,613 | $254 | Implemented |
IC0279 # 01 Y:2023 | 01 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $538 | $1,455 | Implemented |
IC0279 # 05 Y:2023 | 05 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $21,146 | $4,937 | Implemented |
IC0279 # 11 Y:2023 | 11 | 2023 | REPAIR AND ELIMINATE STEAM LEAKS | $10,359 | $750 | Implemented |
OK1060 # 03 Y:2022 | 03 | 2022 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $471 | $0 | Implemented |
IP0149 # 04 Y:2021 | 04 | 2021 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $416 | $380 | Implemented |
IP0149 # 02 Y:2021 | 02 | 2021 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $982 | $120 | Implemented |
IP0149 # 01 Y:2021 | 01 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,671 | $95 | Implemented |
IP0149 # 05 Y:2021 | 05 | 2021 | INSTALL OCCUPANCY SENSORS | $330 | $450 | Implemented |
SD0611 # 07 Y:2021 | 07 | 2021 | PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT | $2,308 | $6,000 | Implemented |
SD0611 # 01 Y:2021 | 01 | 2021 | CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD | $30,193 | $22,050 | Implemented |
SD0611 # 05 Y:2021 | 05 | 2021 | INSTALL OCCUPANCY SENSORS | $203 | $387 | Implemented |
SD0611 # 06 Y:2021 | 06 | 2021 | INSTALL SMALLER BOILER (INCREASE HIGH FIRE DUTY CYCLE) | $45,722 | $186,400 | Implemented |
LE0505 # 05 Y:2021 | 05 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $17,327 | $20,855 | Implemented |
LE0505 # 04 Y:2021 | 04 | 2021 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $62,020 | $55,000 | Implemented |
LE0505 # 03 Y:2021 | 03 | 2021 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $39,439 | $31,000 | Implemented |
LE0505 # 01 Y:2021 | 01 | 2021 | REPAIR OR REPLACE STEAM TRAPS | $72,824 | $26,000 | Implemented |
LE0505 # 02 Y:2021 | 02 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $16,651 | $10,100 | Implemented |
LE0505 # 06 Y:2021 | 06 | 2021 | RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER | $48,123 | $90,000 | Implemented |
OK1046 # 02 Y:2021 | 02 | 2021 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $827 | $0 | Implemented |
OK1046 # 05 Y:2021 | 05 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $16,027 | $38,688 | Implemented |
MI0383 # 06 Y:2020 | 06 | 2020 | INSTALL OCCUPANCY SENSORS | $552 | $882 | Implemented |
MI0383 # 05 Y:2020 | 05 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,327 | $2,436 | Implemented |