IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

33

matching recommendations
Reset
NAICS 326 Plastics and Rubber Products Manufacturing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
CO0720 # 03 Y:2016 03 2016 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $14,190 $67,155 Implemented
CO0720 # 02 Y:2016 02 2016 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $4,840 $300 Implemented
CO0679 # 04 Y:2013 04 2013 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $6,450 $15,070 Implemented
CO0679 # 03 Y:2013 03 2013 AIR CONDITION ONLY SPACE NECESSARY $9,040 $500 Implemented
CO0679 # 02 Y:2013 02 2013 USE RADIANT HEATER FOR SPOT HEATING $1,740 $1,320 Implemented
CO0673 # 03 Y:2013 03 2013 USE COOLING TOWER WATER INSTEAD OF REFRIGERATION $3,060 $4,216 Implemented
CO0673 # 05 Y:2013 05 2013 APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES $5,240 $0 Implemented
CO0673 # 04 Y:2013 04 2013 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,910 $530 Implemented
CO0669 # 03 Y:2013 03 2013 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,650 $390 Implemented
CO0669 # 01 Y:2013 01 2013 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $6,590 $15,280 Implemented
CO0653 # 02 Y:2011 02 2011 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,630 $800 Implemented
CO0650 # 05 Y:2011 05 2011 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS $740 $1,470 Implemented
CO0650 # 03 Y:2011 03 2011 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $4,420 $9,240 Implemented
CO0650 # 02 Y:2011 02 2011 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,390 $190 Implemented
CO0650 # 01 Y:2011 01 2011 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $4,700 $1,000 Implemented
CO0600 # 07 Y:2007 07 2007 USE SOLAR HEAT TO MAKE ELECTRICTY $1,560 $11,000 Implemented
CO0600 # 09 Y:2007 09 2007 USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE $790 $0 Implemented
CO0600 # 05 Y:2007 05 2007 INSTALL COMMON HEADER ON COMPRESSORS $320 $3,450 Implemented
CO0600 # 04 Y:2007 04 2007 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $400 $190 Implemented
CO0600 # 03 Y:2007 03 2007 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $620 $60 Implemented
CO0600 # 02 Y:2007 02 2007 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $2,710 $150 Implemented
CO0588 # 02 Y:2006 02 2006 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $9,500 $50 Implemented
CO0588 # 07 Y:2006 07 2006 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,600 $2,970 Implemented
CO0588 # 06 Y:2006 06 2006 UTILIZE OUTSIDE AIR INSTEAD OF CONDITIONED AIR FOR DRYING $1,680 $1,310 Implemented
CO0588 # 05 Y:2006 05 2006 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $42,290 $57,670 Implemented