Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
8,415
matching recommendationsNAICS | 326 | Plastics and Rubber Products Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SD0347 # 05 Y:2004 | 05 | 2004 | INSTALL AUTOMATIC PACKING EQUIPMENT | $128,000 | $145,000 | Not Implemented |
SD0346 # 01 Y:2004 | 01 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $17,785 | $320 | Implemented |
SD0346 # 02 Y:2004 | 02 | 2004 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $15,306 | $9,465 | Implemented |
SD0346 # 03 Y:2004 | 03 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,189 | $413 | Not Implemented |
SD0346 # 04 Y:2004 | 04 | 2004 | INSTALL SKYLIGHTS | $8,771 | $21,250 | Not Implemented |
SD0346 # 05 Y:2004 | 05 | 2004 | INSTALL AUTOMATIC PACKING EQUIPMENT | $128,000 | $115,000 | Not Implemented |
OR0460 # 01 Y:2004 | 01 | 2004 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,300 | $1,500 | Implemented |
OR0460 # 02 Y:2004 | 02 | 2004 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $5,070 | $1,830 | Implemented |
OR0460 # 03 Y:2004 | 03 | 2004 | TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY | $16,000 | $0 | Implemented |
OR0460 # 04 Y:2004 | 04 | 2004 | INSTALL EQUIPMENT TO MOVE PRODUCT | $37,500 | $14,200 | Not Implemented |
OR0460 # 05 Y:2004 | 05 | 2004 | MOVE PRODUCT USING MECHANICAL MEANS | $7,850 | $2,320 | Implemented |
SD0345 # 01 Y:2004 | 01 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $24,904 | $560 | Implemented |
SD0345 # 02 Y:2004 | 02 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $11,852 | $16,492 | Implemented |
SD0345 # 03 Y:2004 | 03 | 2004 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $8,200 | $2,396 | Not Implemented |
SD0345 # 04 Y:2004 | 04 | 2004 | INSULATE BARE EQUIPMENT | $2,912 | $2,360 | Not Implemented |
SD0345 # 05 Y:2004 | 05 | 2004 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,230 | $1,650 | Implemented |
SD0345 # 06 Y:2004 | 06 | 2004 | INSTALL AUTOMATIC PACKING EQUIPMENT | $235,176 | $320,000 | Not Implemented |
SD0345 # 07 Y:2004 | 07 | 2004 | PAY UTILITY BILLS ON TIME | $2,375 | $0 | Not Implemented |
LL0194 # 01 Y:2004 | 01 | 2004 | INSTALL TIMERS AND/OR THERMOSTATS | $10,188 | $1,430 | Not Implemented |
LL0194 # 02 Y:2004 | 02 | 2004 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $8,957 | $570 | Implemented |
LL0194 # 03 Y:2004 | 03 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,000 | $2,360 | Implemented |
LL0194 # 04 Y:2004 | 04 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,025 | $770 | Implemented |
LL0194 # 05 Y:2004 | 05 | 2004 | USE PHOTOCELL CONTROLS | $729 | $60 | Implemented |
LL0194 # 06 Y:2004 | 06 | 2004 | USE PHOTOCELL CONTROLS | $419 | $180 | Implemented |
LL0194 # 07 Y:2004 | 07 | 2004 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $764 | $158 | Implemented |