Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
38
matching recommendationsNAICS | 3261 | Plastics Product Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK1094 # 03 Y:2023 | 03 | 2023 | INSTALL TIMERS AND/OR THERMOSTATS | $573 | $870 | Implemented |
OK1094 # 02 Y:2023 | 02 | 2023 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $3,917 | $22,000 | Implemented |
OK1094 # 04 Y:2023 | 04 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $26,890 | $94,115 | Implemented |
TT0241 # 11 Y:2020 | 11 | 2020 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $307 | $680 | Implemented |
TT0241 # 12 Y:2020 | 12 | 2020 | INSTALL / REPAIR INSULATION ON STEAM LINES | $74 | $269 | Implemented |
TT0241 # 10 Y:2020 | 10 | 2020 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $404 | $1,000 | Implemented |
TT0241 # 09 Y:2020 | 09 | 2020 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,651 | $6,000 | Implemented |
TT0241 # 08 Y:2020 | 08 | 2020 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,202 | $20 | Implemented |
TT0241 # 04 Y:2020 | 04 | 2020 | REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT | $18,441 | $75,000 | Implemented |
TT0241 # 07 Y:2020 | 07 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,304 | $3,360 | Implemented |
TT0241 # 05 Y:2020 | 05 | 2020 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $8,106 | $530 | Implemented |
TT0241 # 02 Y:2020 | 02 | 2020 | UPGRADE CONTROLS ON COMPRESSORS | $54,178 | $300 | Implemented |
TT0241 # 03 Y:2020 | 03 | 2020 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $49,818 | $14,600 | Implemented |
OK0934 # 03 Y:2016 | 03 | 2016 | ELIMINATE COOLING OF PROCESS STREAMS WHICH SUBSEQUENTLY MUST BE HEATED AND VICE VERSA | $134,039 | $1,300 | Implemented |
OK0934 # 04 Y:2016 | 04 | 2016 | INSULATE BARE EQUIPMENT | $63,243 | $3,161 | Implemented |
OK0921 # 01 Y:2015 | 01 | 2015 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $7,838 | $28,060 | Implemented |
OK0921 # 03 Y:2015 | 03 | 2015 | INSULATE BARE EQUIPMENT | $13,915 | $4,348 | Implemented |
OK0921 # 04 Y:2015 | 04 | 2015 | INSTALL DESICCANT HUMIDITY CONTROL SYSTEM | $89,313 | $72,000 | Implemented |
OK0921 # 05 Y:2015 | 05 | 2015 | REDUCE FLUID FLOW RATES | $32,332 | $5,000 | Implemented |
TT0090 # 03 Y:2012 | 03 | 2012 | USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY | $1,275 | $1,000 | Implemented |
TT0090 # 05 Y:2012 | 05 | 2012 | INSTALL OCCUPANCY SENSORS | $1,008 | $1,780 | Implemented |
TT0090 # 04 Y:2012 | 04 | 2012 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $2,764 | $2,000 | Implemented |
TT0090 # 09 Y:2012 | 09 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $134 | $525 | Implemented |
TT0090 # 02 Y:2012 | 02 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $334 | $0 | Implemented |
TT0090 # 08 Y:2012 | 08 | 2012 | DEVELOP A REPAIR/REPLACE POLICY | $2,350 | $2,400 | Implemented |