Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
126
matching recommendationsNAICS | 3261 | Plastics Product Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
NC0641 # 02 Y:2019 | 02 | 2019 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $18,554 | $21,000 | Not Implemented |
NC0641 # 03 Y:2019 | 03 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $29,143 | $35,000 | Implemented |
NC0641 # 04 Y:2019 | 04 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,183 | $16,246 | Not Implemented |
NC0641 # 01 Y:2019 | 01 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,164 | $120 | Not Implemented |
NC0611 # 04 Y:2018 | 04 | 2018 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $7,227 | $35,000 | Not Implemented |
NC0611 # 05 Y:2018 | 05 | 2018 | DEVELOP A REPAIR/REPLACE POLICY | $2,887 | $5,685 | Implemented |
NC0611 # 01 Y:2018 | 01 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $58,179 | $92,653 | Implemented |
NC0611 # 06 Y:2018 | 06 | 2018 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $1,662 | $200 | Implemented |
NC0611 # 02 Y:2018 | 02 | 2018 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $12,370 | $200 | Implemented |
NC0611 # 03 Y:2018 | 03 | 2018 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $7,064 | $100 | Not Implemented |
NC0554 # 05 Y:2015 | 05 | 2015 | RECYCLE AIR FOR HEATING, VENTILATION AND AIR CONDITIONING | $3,916 | $4,500 | Not Implemented |
NC0554 # 08 Y:2015 | 08 | 2015 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $147 | $150 | Implemented |
NC0554 # 07 Y:2015 | 07 | 2015 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $5,043 | $9,000 | Not Implemented |
NC0554 # 10 Y:2015 | 10 | 2015 | DEVELOP A REPAIR/REPLACE POLICY | $2,829 | $4,258 | Implemented |
NC0554 # 04 Y:2015 | 04 | 2015 | RECOVER WASTE HEAT FROM EQUIPMENT | $8,465 | $12,000 | Implemented |
NC0554 # 01 Y:2015 | 01 | 2015 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $5,085 | $12,500 | Implemented |
NC0554 # 09 Y:2015 | 09 | 2015 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $587 | $100 | Not Implemented |
NC0554 # 02 Y:2015 | 02 | 2015 | INSULATE BARE EQUIPMENT | $10,751 | $8,568 | Not Implemented |
NC0554 # 06 Y:2015 | 06 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,384 | $100 | Implemented |
NC0554 # 03 Y:2015 | 03 | 2015 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,597 | $4,400 | Implemented |
TT0134 # 01 Y:2014 | 01 | 2014 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $9,053 | $1,894 | Not Implemented |
TT0134 # 03 Y:2014 | 03 | 2014 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $96,724 | $822 | Implemented |
TT0134 # 02 Y:2014 | 02 | 2014 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $36,133 | $17,000 | Not Implemented |
WV0482 # 16 Y:2014 | 16 | 2014 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $507 | $1,167 | Implemented |
WV0482 # 01 Y:2014 | 01 | 2014 | USE "HEAT WHEEL" OR OTHER HEAT EXCHANGER TO CROSS-EXCHANGE BUILDING EXHAUST AIR WITH MAKE-UP AIR | $177,357 | $198,000 | Not Implemented |