Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,122
matching recommendationsNAICS | 32611 | Plastics Packaging Materials and Unlaminated Film and Sheet Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WM0195 # 09 Y:2023 | 09 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,142 | $1,715 | Not Implemented |
WM0195 # 01 Y:2023 | 01 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $15,725 | $13,127 | Implemented |
WM0195 # 02 Y:2023 | 02 | 2023 | USE RADIANT HEATER FOR SPOT HEATING | $15,091 | $13,400 | Not Implemented |
WM0195 # 03 Y:2023 | 03 | 2023 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $5,128 | $1,700 | Not Implemented |
WM0195 # 04 Y:2023 | 04 | 2023 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $4,436 | $3,735 | Not Implemented |
UU0214 # 01 Y:2023 | 01 | 2023 | OPTIMIZE PLANT POWER FACTOR | $14,031 | $23,302 | Implemented |
UU0214 # 02 Y:2023 | 02 | 2023 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $4,069 | $17,638 | Implemented |
UU0214 # 03 Y:2023 | 03 | 2023 | TURN OFF EQUIPMENT WHEN NOT IN USE | $2,776 | $6,969 | Implemented |
UU0214 # 04 Y:2023 | 04 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,274 | $495 | Implemented |
UU0214 # 05 Y:2023 | 05 | 2023 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $701 | $1,150 | Not Implemented |
UU0214 # 06 Y:2023 | 06 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $550 | $1,558 | Implemented |
UU0214 # 07 Y:2023 | 07 | 2023 | STORE HEATED/ COOLED WATER FOR USE DURING PEAK DEMAND PERIODS | $24,046 | $226,100 | Not Implemented |
UU0214 # 08 Y:2023 | 08 | 2023 | SHUT OFF COOLING IF COLD OUTSIDE AIR WILL COOL PROCESS | $23,820 | $214,625 | Not Implemented |
DL0212 # 01 Y:2022 | 01 | 2022 | REPAIR FAULTY LOUVERS AND DAMPERS | $20,616 | $975 | Not Implemented |
DL0212 # 02 Y:2022 | 02 | 2022 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $4,912 | $5,000 | Not Implemented |
DL0212 # 03 Y:2022 | 03 | 2022 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $634 | $495 | Not Implemented |
DL0212 # 04 Y:2022 | 04 | 2022 | RECOVER WASTE HEAT FROM EQUIPMENT | $5,199 | $6,100 | Not Implemented |
DL0212 # 05 Y:2022 | 05 | 2022 | RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | $3,655 | $5,200 | Not Implemented |
DL0212 # 06 Y:2022 | 06 | 2022 | USE OPTIMUM THICKNESS INSULATION | $692 | $2,233 | Not Implemented |
DL0212 # 07 Y:2022 | 07 | 2022 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $11,396 | $21,500 | Not Implemented |
DL0212 # 08 Y:2022 | 08 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $7,587 | $13,450 | Not Implemented |
DL0212 # 09 Y:2022 | 09 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $278 | $210 | Not Implemented |
DL0212 # 10 Y:2022 | 10 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $20,304 | $22,424 | Not Implemented |
MZ0335 # 01 Y:2022 | 01 | 2022 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $558 | $480 | Implemented |
MZ0335 # 02 Y:2022 | 02 | 2022 | RECOVER WASTE HEAT FROM EQUIPMENT | $4,654 | $7,600 | Implemented |