Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
155
matching recommendationsNAICS | 326111 | Plastics Bag and Pouch Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SD0347 # 01 Y:2004 | 01 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,911 | $450 | Implemented |
SD0347 # 02 Y:2004 | 02 | 2004 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $5,552 | $0 | Implemented |
SD0346 # 01 Y:2004 | 01 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $17,785 | $320 | Implemented |
SD0346 # 02 Y:2004 | 02 | 2004 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $15,306 | $9,465 | Implemented |
SD0345 # 01 Y:2004 | 01 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $24,904 | $560 | Implemented |
SD0345 # 02 Y:2004 | 02 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $11,852 | $16,492 | Implemented |
SD0345 # 05 Y:2004 | 05 | 2004 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,230 | $1,650 | Implemented |
NC0269 # 01 Y:2003 | 01 | 2003 | INSTALL REFRIGERATION SYSTEM TO COOL PRODUCT | $272,200 | $118,250 | Implemented |
NC0269 # 02 Y:2003 | 02 | 2003 | INSULATE BARE EQUIPMENT | $16,965 | $5,128 | Implemented |
NC0269 # 03 Y:2003 | 03 | 2003 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $14,974 | $9,174 | Implemented |
NC0269 # 04 Y:2003 | 04 | 2003 | DEVELOP A REPAIR/REPLACE POLICY | $4,027 | $1,719 | Implemented |
NC0269 # 06 Y:2003 | 06 | 2003 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $3,654 | $2,400 | Implemented |
LM0065 # 01 Y:2004 | 01 | 2004 | DISCONNECT BALLASTS | $517 | $200 | Implemented |
LM0065 # 02 Y:2004 | 02 | 2004 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $713 | $110 | Implemented |
LM0065 # 03 Y:2004 | 03 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,088 | $3,616 | Implemented |
LM0065 # 04 Y:2004 | 04 | 2004 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $241 | $118 | Implemented |
LM0065 # 05 Y:2004 | 05 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $327 | $270 | Implemented |
NC0261 # 01 Y:2003 | 01 | 2003 | DEVELOP A REPAIR/REPLACE POLICY | $10,483 | $9,992 | Implemented |
NC0261 # 04 Y:2003 | 04 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,891 | $50 | Implemented |
NC0261 # 05 Y:2003 | 05 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,466 | $6,430 | Implemented |
NC0259 # 01 Y:2003 | 01 | 2003 | INSULATE BARE EQUIPMENT | $7,357 | $1,650 | Implemented |
NC0259 # 02 Y:2003 | 02 | 2003 | DEVELOP A REPAIR/REPLACE POLICY | $3,711 | $5,940 | Implemented |
NC0259 # 04 Y:2003 | 04 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,905 | $50 | Implemented |
NC0259 # 07 Y:2003 | 07 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $887 | $862 | Implemented |
NC0259 # 08 Y:2003 | 08 | 2003 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,879 | $1,740 | Implemented |