Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
180
matching recommendationsNAICS | 326122 | Plastics Pipe and Pipe Fitting Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IA0453 # 01 Y:2010 | 01 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,157 | $19,968 | Implemented |
IA0453 # 02 Y:2010 | 02 | 2010 | INSTALL OCCUPANCY SENSORS | $1,082 | $1,037 | Implemented |
IA0453 # 04 Y:2010 | 04 | 2010 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $5,525 | $11,586 | Implemented |
IA0453 # 08 Y:2010 | 08 | 2010 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $678 | $81 | Implemented |
IA0453 # 09 Y:2010 | 09 | 2010 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $1,215 | $3,400 | Implemented |
MZ0043 # 01 Y:2009 | 01 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,595 | $20,400 | Implemented |
MZ0043 # 02 Y:2009 | 02 | 2009 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,634 | $860 | Implemented |
MZ0043 # 03 Y:2009 | 03 | 2009 | INSTALL OCCUPANCY SENSORS | $2,319 | $480 | Implemented |
MZ0043 # 04 Y:2009 | 04 | 2009 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $627 | $1,800 | Implemented |
MZ0043 # 05 Y:2009 | 05 | 2009 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $7,387 | $3,600 | Implemented |
MZ0043 # 06 Y:2009 | 06 | 2009 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $3,995 | $1 | Implemented |
MZ0043 # 08 Y:2009 | 08 | 2009 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $192,075 | $12,080 | Implemented |
MZ0043 # 09 Y:2009 | 09 | 2009 | MOVE BOILER TO MORE EFFICIENT LOCATION | $10,937 | $3,000 | Implemented |
TT0035 # 01 Y:2008 | 01 | 2008 | $15,307 | $5,600 | Implemented | |
TT0035 # 02 Y:2008 | 02 | 2008 | $5,446 | $12,785 | Implemented | |
TT0035 # 05 Y:2008 | 05 | 2008 | $7,885 | $25,000 | Implemented | |
UF0418 # 02 Y:2008 | 02 | 2008 | INSTALL COMMON HEADER ON COMPRESSORS | $4,076 | $2,560 | Implemented |
UF0418 # 03 Y:2008 | 03 | 2008 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,047 | $1,060 | Implemented |
UF0418 # 05 Y:2008 | 05 | 2008 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,900 | $800 | Implemented |
UF0418 # 07 Y:2008 | 07 | 2008 | ADJUST / MAINTAIN FORK LIFT TRUCKS FOR MOST EFFICIENT OPERATION | $3,791 | $0 | Implemented |
UF0418 # 08 Y:2008 | 08 | 2008 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $39,146 | $1,589 | Implemented |
UF0418 # 09 Y:2008 | 09 | 2008 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $7,856 | $809 | Implemented |
UF0418 # 11 Y:2008 | 11 | 2008 | INSTALL OCCUPANCY SENSORS | $5,889 | $6,806 | Implemented |
UF0418 # 12 Y:2008 | 12 | 2008 | DEVELOP A REPAIR/REPLACE POLICY | $729 | $0 | Implemented |
UF0418 # 15 Y:2008 | 15 | 2008 | MAINTAIN MACHINES TO REDUCE LEAKS | $6,175 | $161 | Implemented |