Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
211
matching recommendationsNAICS | 32615 | Urethane and Other Foam Product (except Polystyrene) Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
TT0049 # 06 Y:2010 | 06 | 2010 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $10,723 | $0 | Not Implemented |
UW0029 # 01 Y:2009 | 01 | 2009 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $13,416 | $120,000 | Implemented |
UW0029 # 02 Y:2009 | 02 | 2009 | INSTALL MOTOR VOLTAGE CONTROLLER ON LIGHTLY LOADED MOTORS | $10,263 | $17,000 | Implemented |
UW0029 # 03 Y:2009 | 03 | 2009 | INSULATE BARE EQUIPMENT | $3,269 | $3,800 | Implemented |
UW0029 # 04 Y:2009 | 04 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,713 | $9,934 | Implemented |
UM0343 # 01 Y:2008 | 01 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $13,158 | $32,000 | Not Implemented |
UM0343 # 02 Y:2008 | 02 | 2008 | RECOVER WASTE HEAT FROM EQUIPMENT | $10,585 | $10,000 | Not Implemented |
UM0343 # 03 Y:2008 | 03 | 2008 | USE OPTIMUM THICKNESS INSULATION | $8,476 | $9,576 | Not Implemented |
UM0343 # 04 Y:2008 | 04 | 2008 | USE RADIANT HEATER FOR SPOT HEATING | $3,750 | $0 | Implemented |
UM0343 # 05 Y:2008 | 05 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,390 | $5,864 | Not Implemented |
UM0343 # 06 Y:2008 | 06 | 2008 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,378 | $750 | Implemented |
UF0415 # 01 Y:2008 | 01 | 2008 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $662 | $300 | Not Implemented |
UF0415 # 02 Y:2008 | 02 | 2008 | PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT | $19,825 | $20,000 | Not Implemented |
UF0415 # 03 Y:2008 | 03 | 2008 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $7,271 | $400 | Not Implemented |
UF0415 # 04 Y:2008 | 04 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $34,736 | $30,084 | Implemented |
UF0415 # 05 Y:2008 | 05 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $666 | $0 | Implemented |
UF0415 # 06 Y:2008 | 06 | 2008 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $27,511 | $182,894 | Not Implemented |
UF0415 # 07 Y:2008 | 07 | 2008 | DEVELOP A REPAIR/REPLACE POLICY | $648 | $0 | Implemented |
UF0415 # 08 Y:2008 | 08 | 2008 | INSTALL COMMON HEADER ON COMPRESSORS | $6,290 | $550 | Not Implemented |
UF0415 # 09 Y:2008 | 09 | 2008 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $49,178 | $49,400 | Not Implemented |
DL0012 # 01 Y:2008 | 01 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $27,593 | $26,675 | Implemented |
DL0012 # 02 Y:2008 | 02 | 2008 | USE "HEAT WHEEL" OR OTHER HEAT EXCHANGER TO CROSS-EXCHANGE BUILDING EXHAUST AIR WITH MAKE-UP AIR | $19,600 | $23,900 | Not Implemented |
DL0012 # 03 Y:2008 | 03 | 2008 | RE-SIZE CHARGING OPENINGS OR ADD MOVABLE COVER OR DOOR | $5,988 | $146 | Not Implemented |
DL0012 # 04 Y:2008 | 04 | 2008 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $6,766 | $16,500 | Not Implemented |
DL0012 # 05 Y:2008 | 05 | 2008 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $3,154 | $0 | Not Implemented |