Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
71
matching recommendationsNAICS | 3273 | Cement and Concrete Product Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UW2317 # 04 Y:2023 | 04 | 2023 | CHANGE PRODUCT DESIGN TO REDUCE ENERGY REQUIREMENTS | $31,756 | $1,000,000 | Implemented |
UW2317 # 03 Y:2023 | 03 | 2023 | INSTALL STORM WINDOWS AND DOORS | $156 | $1,901 | Implemented |
UW2317 # 02 Y:2023 | 02 | 2023 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $658 | $1,096 | Implemented |
UW2317 # 01 Y:2023 | 01 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $533 | $0 | Implemented |
UW2317 # 05 Y:2023 | 05 | 2023 | IMPROVE COMBUSTION CONTROL CAPABILITY | $30,104 | $300,000 | Implemented |
UW2315 # 03 Y:2023 | 03 | 2023 | USE DOUBLE OR TRIPLE GLAZED WINDOWS TO MAINTAIN HIGHER RELATIVE HUMIDITY AND TO REDUCE HEAT LOSSES | $1,343 | $10,879 | Not Implemented |
UW2315 # 02 Y:2023 | 02 | 2023 | IMPROVE COMBUSTION CONTROL CAPABILITY | $30,104 | $300,000 | Implemented |
UW2315 # 01 Y:2023 | 01 | 2023 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $6,189 | $1,896 | Implemented |
CM1022 # 04 Y:2023 | 04 | 2023 | REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT | $4,255 | $4,988 | n/a |
CM1022 # 01 Y:2023 | 01 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $10,354 | $115,732 | n/a |
CM1022 # 02 Y:2023 | 02 | 2023 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $8,106 | $92,608 | n/a |
CM1022 # 05 Y:2023 | 05 | 2023 | REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT | $1,995 | $2,168 | n/a |
CM1022 # 06 Y:2023 | 06 | 2023 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $3,118 | $1,776 | n/a |
CM1022 # 03 Y:2023 | 03 | 2023 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $3,609 | $32,760 | n/a |
CM1022 # 07 Y:2023 | 07 | 2023 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $2,174 | $8,000 | n/a |
WM0204 # 02 Y:2023 | 02 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,440 | $2,330 | Implemented |
WM0204 # 01 Y:2023 | 01 | 2023 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $22,875 | $1,950 | Not Implemented |
WM0204 # 03 Y:2023 | 03 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $651 | $1,001 | Not Implemented |
WM0204 # 05 Y:2023 | 05 | 2023 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $97 | $240 | Implemented |
WM0204 # 04 Y:2023 | 04 | 2023 | INSTALL OCCUPANCY SENSORS | $571 | $750 | Implemented |
AS0555 # 02 Y:2023 | 02 | 2023 | ADD AIR SHIELDS TO TRUCKS TO INCREASE FUEL MILEAGE | $10,191 | $10,364 | Not Implemented |
AS0555 # 06 Y:2023 | 06 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,078 | $399 | Not Implemented |
AS0556 # 01 Y:2023 | 01 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $53,360 | $14,735 | Not Implemented |
AS0555 # 01 Y:2023 | 01 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $29,191 | $11,546 | Not Implemented |
AS0556 # 05 Y:2023 | 05 | 2023 | USE PHOTOCELL CONTROLS | $4,658 | $7,034 | Not Implemented |