Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
4,725
matching recommendationsNAICS | 331 | Primary Metal Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WV0668 # 09 Y:2024 | 09 | 2024 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $239 | $824 | Implemented |
WV0668 # 10 Y:2024 | 10 | 2024 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $113 | $152 | Implemented |
IP0199 # 01 Y:2024 | 01 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,242 | $85 | n/a |
IP0199 # 02 Y:2024 | 02 | 2024 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $287 | $25 | n/a |
UU0256 # 01 Y:2024 | 01 | 2024 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $43,875 | $401,481 | n/a |
UU0256 # 02 Y:2024 | 02 | 2024 | OPTIMIZE PLANT POWER FACTOR | $14,319 | $31,625 | n/a |
UU0256 # 03 Y:2024 | 03 | 2024 | USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER | $8,048 | $11,730 | n/a |
UU0256 # 04 Y:2024 | 04 | 2024 | REDUCE EXCESSIVE BOILER BLOWDOWN | $5,024 | $7,960 | n/a |
IP0199 # 03 Y:2024 | 03 | 2024 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $6,822 | $2,157 | n/a |
IP0199 # 04 Y:2024 | 04 | 2024 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $7,284 | $4,422 | n/a |
IP0199 # 05 Y:2024 | 05 | 2024 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $4,328 | $3,600 | n/a |
IP0199 # 06 Y:2024 | 06 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $10,187 | $12,000 | n/a |
IP0199 # 07 Y:2024 | 07 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $706 | $1,069 | n/a |
IP0199 # 08 Y:2024 | 08 | 2024 | INSTALL OCCUPANCY SENSORS | $257 | $668 | n/a |
IP0199 # 09 Y:2024 | 09 | 2024 | REPLACE BOILER | $434,522 | $2,000,000 | n/a |
UL2408 # 01 Y:2024 | 01 | 2024 | USE OUTSIDE COLD WATER SOURCE AS A SUPPLY OF COOLING WATER | $77,905 | $42,617 | n/a |
UL2408 # 02 Y:2024 | 02 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $319,482 | $2,990,386 | n/a |
UL2408 # 03 Y:2024 | 03 | 2024 | RECOVER WASTE HEAT FROM EQUIPMENT | $40,749 | $39,000 | n/a |
NT0026 # 01 Y:2024 | 01 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $10,160 | $5,609 | Implemented |
NT0026 # 02 Y:2024 | 02 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $22,341 | $0 | Implemented |
NT0026 # 03 Y:2024 | 03 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $109,656 | $54,987 | Implemented |
NT0026 # 04 Y:2024 | 04 | 2024 | OPTIMIZE PLANT POWER FACTOR | $122,072 | $90,330 | Not Implemented |
NT0026 # 05 Y:2024 | 05 | 2024 | APPLY FOR INVESTMENT INCENTIVES | $133,205 | $0 | Not Implemented |
UA0286 # 01 Y:2024 | 01 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $35,619 | $21,591 | Implemented |
UA0286 # 02 Y:2024 | 02 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $25,164 | $3,000 | Implemented |