matching recommendationsNAICS | 331314 | Secondary Smelting and Alloying of Aluminum |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UD0774 # 03 Y:2008 | 03 | 2008 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $83,440 | $5,000 | Implemented |
UD0774 # 04 Y:2008 | 04 | 2008 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $15,764 | $4,008 | Not Implemented |
UD0774 # 05 Y:2008 | 05 | 2008 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $9,705 | $3,275 | Implemented |
UD0774 # 06 Y:2008 | 06 | 2008 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $9,454 | $0 | Implemented |
UD0774 # 07 Y:2008 | 07 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,208 | $12,758 | Not Implemented |
UD0774 # 08 Y:2008 | 08 | 2008 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $8,237 | $0 | Not Implemented |
UD0774 # 09 Y:2008 | 09 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,863 | $6,540 | Not Implemented |
UD0774 # 10 Y:2008 | 10 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,371 | $2,250 | Implemented |
UD0774 # 11 Y:2008 | 11 | 2008 | USE SEPARATE SWITCHES ON PERIMETER LIGHTING WHICH MAY BE TURNED OFF WHEN NATURAL LIGHT IS AVAILABLE | $3,078 | $0 | Implemented |
LE0261 # 01 Y:2007 | 01 | 2007 | PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER | $196,792 | $500 | Not Implemented |
LE0261 # 02 Y:2007 | 02 | 2007 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $71,526 | $75,000 | Not Implemented |
LE0261 # 03 Y:2007 | 03 | 2007 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $17,454 | $12,000 | Not Implemented |
LE0261 # 04 Y:2007 | 04 | 2007 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $15,461 | $20 | Implemented |
LE0261 # 05 Y:2007 | 05 | 2007 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $8,661 | $100 | Implemented |
LE0261 # 06 Y:2007 | 06 | 2007 | RECOVER WASTE HEAT FROM EQUIPMENT | $7,137 | $5,000 | Not Implemented |
LE0261 # 07 Y:2007 | 07 | 2007 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $6,155 | $1,500 | Implemented |
LE0261 # 08 Y:2007 | 08 | 2007 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,476 | $150 | Implemented |
LE0261 # 09 Y:2007 | 09 | 2007 | SHIFT FROM DAYTIME TO NIGHTTIME OPERATION | $3,985 | $300 | Not Implemented |
LM0125 # 01 Y:2007 | 01 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,003 | $2,604 | Implemented |
LM0125 # 02 Y:2007 | 02 | 2007 | INSTALL BACK-UP EQUIPMENT | $20,000 | $20,000 | Not Implemented |
LM0125 # 03 Y:2007 | 03 | 2007 | INSTALL EQUIPMENT TO MOVE PRODUCT | $89,704 | $11,000 | Implemented |
LM0125 # 04 Y:2007 | 04 | 2007 | USE HEAT IN FLUE GASES TO PREHEAT PRODUCTS OR MATERIALS | $62,618 | $40,000 | Not Implemented |
UM0305 # 01 Y:2006 | 01 | 2006 | INSULATE BARE EQUIPMENT | $26,404 | $1,300 | Implemented |
UM0305 # 02 Y:2006 | 02 | 2006 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $25,149 | $46,400 | Not Implemented |
UM0305 # 03 Y:2006 | 03 | 2006 | INSULATE BARE EQUIPMENT | $17,877 | $1,112 | Implemented |