Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
80
matching recommendationsNAICS | 33149 | Nonferrous Metal (except Copper and Aluminum) Rolling, Drawing, Extruding, and Alloying |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MZ0107 # 05 Y:2013 | 05 | 2013 | INSTALL OCCUPANCY SENSORS | $4,907 | $3,080 | Implemented |
MZ0107 # 09 Y:2013 | 09 | 2013 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,541 | $1,810 | Implemented |
MZ0107 # 10 Y:2013 | 10 | 2013 | USE OPTIMUM THICKNESS INSULATION | $1,288 | $1,499 | Implemented |
MZ0107 # 06 Y:2013 | 06 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,600 | $1,745 | Implemented |
MZ0107 # 08 Y:2013 | 08 | 2013 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,356 | $710 | Implemented |
MZ0107 # 12 Y:2013 | 12 | 2013 | USE PHOTOCELL CONTROLS | $265 | $320 | Implemented |
MZ0107 # 11 Y:2013 | 11 | 2013 | REPAIR FURNACES AND OVEN DOORS SO THAT THEY SEAL EFFICIENTLY | $845 | $1,115 | Implemented |
MZ0107 # 02 Y:2013 | 02 | 2013 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $43,709 | $1,000 | Implemented |
MZ0107 # 04 Y:2013 | 04 | 2013 | USE OPTIMUM THICKNESS INSULATION | $6,130 | $1,825 | Implemented |
AM0622 # 04 Y:2012 | 04 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,720 | $520 | Implemented |
AM0622 # 09 Y:2012 | 09 | 2012 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $560 | $0 | Implemented |
AM0622 # 07 Y:2012 | 07 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,780 | $870 | Implemented |
AM0622 # 03 Y:2012 | 03 | 2012 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $25,450 | $69,300 | Implemented |
DL0065 # 08 Y:2011 | 08 | 2011 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $510 | $50 | Implemented |
DL0065 # 06 Y:2011 | 06 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,834 | $2,409 | Implemented |
DL0065 # 04 Y:2011 | 04 | 2011 | DEVELOP A REPAIR/REPLACE POLICY | $3,970 | $1,158 | Implemented |
SU0301 # 03 Y:2011 | 03 | 2011 | INSTALL OCCUPANCY SENSORS | $2,477 | $2,028 | Implemented |
LE0310 # 01 Y:2010 | 01 | 2010 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $26,531 | $10,000 | Implemented |
LE0310 # 02 Y:2010 | 02 | 2010 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $5,363 | $200 | Implemented |
LE0310 # 03 Y:2010 | 03 | 2010 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,484 | $1,420 | Implemented |
LE0310 # 04 Y:2010 | 04 | 2010 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $3,986 | $2,500 | Implemented |
LE0310 # 05 Y:2010 | 05 | 2010 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,225 | $20 | Implemented |
CO0621 # 06 Y:2009 | 06 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $400 | $510 | Implemented |
CO0621 # 02 Y:2009 | 02 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,570 | $3,690 | Implemented |
LE0274 # 06 Y:2008 | 06 | 2008 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $189 | $280 | Implemented |