Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
22
matching recommendationsNAICS | 33232 | Ornamental and Architectural Metal Products Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UD1068 # 04 Y:2023 | 04 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,629 | $100 | Implemented |
UD0945 # 12 Y:2016 | 12 | 2016 | DEVELOP A REPAIR/REPLACE POLICY | $3,983 | $20,370 | Implemented |
UD0945 # 11 Y:2016 | 11 | 2016 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $5,976 | $0 | Implemented |
UD0945 # 04 Y:2016 | 04 | 2016 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $623 | $30 | Implemented |
UD0945 # 03 Y:2016 | 03 | 2016 | REDUCE FLUID FLOW RATES | $7,163 | $0 | Implemented |
UD0945 # 02 Y:2016 | 02 | 2016 | CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE | $527 | $0 | Implemented |
UD0945 # 01 Y:2016 | 01 | 2016 | UTILIZE A LESS EXPENSIVE COOLING METHOD | $5,063 | $8,000 | Implemented |
UD0855 # 04 Y:2012 | 04 | 2012 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,089 | $0 | Implemented |
UD0855 # 08 Y:2012 | 08 | 2012 | REDUCE VENTILATION AIR | $2,956 | $6,600 | Implemented |
UD0855 # 06 Y:2012 | 06 | 2012 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $3,118 | $0 | Implemented |
UD0855 # 05 Y:2012 | 05 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,665 | $1,000 | Implemented |
UD0855 # 01 Y:2012 | 01 | 2012 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $23,100 | $0 | Implemented |
UD0845 # 03 Y:2011 | 03 | 2011 | INSTALL ADEQUATE DRYERS ON AIR LINES TO ELIMINATE BLOWDOWN | $4,285 | $4,000 | Implemented |
UD0845 # 02 Y:2011 | 02 | 2011 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $534 | $0 | Implemented |
UD0831 # 08 Y:2011 | 08 | 2011 | CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS | $137 | $25 | Implemented |
UD0831 # 07 Y:2011 | 07 | 2011 | TURN OFF EQUIPMENT WHEN NOT IN USE | $189 | $240 | Implemented |
UD0831 # 04 Y:2011 | 04 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $713 | $10,495 | Implemented |
UD0831 # 03 Y:2011 | 03 | 2011 | INSTALL SPECTRAL REFLECTORS / DELAMP | $4,392 | $3,863 | Implemented |
UD0729 # 05 Y:2005 | 05 | 2005 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $19,115 | $0 | Implemented |
UD0729 # 10 Y:2005 | 10 | 2005 | INSULATE BARE EQUIPMENT | $487 | $0 | Implemented |
UD0729 # 07 Y:2005 | 07 | 2005 | DISCONNECT BALLASTS | $8,190 | $2,250 | Implemented |
UD0729 # 06 Y:2005 | 06 | 2005 | UPGRADE CONTROLS ON COMPRESSORS | $11,374 | $1,725 | Implemented |