IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

40

matching recommendations
Reset
NAICS 3328 Coating, Engraving, Heat Treating, and Allied Activities
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
MA0735 # 05 Y:2014 05 2014 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,377 $4,200 Implemented
MA0735 # 04 Y:2014 04 2014 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $1,027 $3,000 Implemented
MA0735 # 02 Y:2014 02 2014 INSTALL / REPAIR INSULATION ON STEAM LINES $3,745 $3,519 Implemented
MA0735 # 03 Y:2014 03 2014 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE $3,084 $500 Implemented
MAS035 # 02 Y:2012 02 2012 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $1,443 $0 Implemented
MAS035 # 01 Y:2012 01 2012 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $5,986 $2,000 Implemented
MA0665 # 01 Y:2010 01 2010 UPGRADE CONTROLS ON COMPRESSORS $15,680 $58,600 Implemented
MA0665 # 06 Y:2010 06 2010 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,028 $480 Implemented
MA0665 # 02 Y:2010 02 2010 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $3,642 $18,330 Implemented
MA0665 # 04 Y:2010 04 2010 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $1,470 $200 Implemented
MA0665 # 07 Y:2010 07 2010 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS $155 $180 Implemented
MA0621 # 03 Y:2007 03 2007 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS $3,253 $10,000 Implemented
MA0621 # 05 Y:2007 05 2007 INSTALL / REPAIR INSULATION ON CONDENSATE LINES $405 $280 Implemented
MA0588 # 02 Y:2005 02 2005 USE MINIMUM STEAM OPERATING PRESSURE $2,294 $500 Implemented
MA0588 # 01 Y:2005 01 2005 INSULATE BARE EQUIPMENT $3,404 $2,197 Implemented
MA0588 # 04 Y:2005 04 2005 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,132 $4,668 Implemented
MA0586 # 02 Y:2005 02 2005 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES $3,081 $140 Implemented
MA0586 # 03 Y:2005 03 2005 ELIMINATE LEAKS IN WATER LINES AND VALVES $3,200 $0 Implemented
MA0586 # 05 Y:2005 05 2005 COMBINE UTILITY METERS $1,736 $1,950 Implemented
MA0586 # 06 Y:2005 06 2005 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $841 $1,646 Implemented
MA0586 # 07 Y:2005 07 2005 INSTALL OCCUPANCY SENSORS $443 $1,395 Implemented
MA0560 # 02 Y:2004 02 2004 USE DIRECT AIR SUPPLY TO EXHAUST HOODS $32,756 $23,710 Implemented
MA0560 # 03 Y:2004 03 2004 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $5,875 $1,200 Implemented
MA0560 # 04 Y:2004 04 2004 INSTALL OCCUPANCY SENSORS $317 $256 Implemented
MA0560 # 05 Y:2004 05 2004 DIRECT WARMEST AIR TO COMBUSTION INTAKE $230 $175 Implemented