Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
56
matching recommendationsNAICS | 33281 | Coating, Engraving, Heat Treating, and Allied Activities |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IP0123 # 02 Y:2019 | 02 | 2019 | DE-ENERGIZE EXCESS TRANSFORMER CAPACITY | $248 | $0 | Implemented |
IP0123 # 01 Y:2019 | 01 | 2019 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $286 | $7 | Implemented |
IP0123 # 05 Y:2019 | 05 | 2019 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $1,980 | $440 | Implemented |
IP0123 # 03 Y:2019 | 03 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $442 | $70 | Implemented |
IP0123 # 09 Y:2019 | 09 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,165 | $13,663 | Implemented |
IP0123 # 08 Y:2019 | 08 | 2019 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $758 | $2,290 | Implemented |
IC0211 # 03 Y:2019 | 03 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $25,768 | $42,206 | Implemented |
IC0211 # 04 Y:2019 | 04 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $5,829 | $4,500 | Implemented |
IC0211 # 05 Y:2019 | 05 | 2019 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $36,922 | $0 | Implemented |
IC0211 # 02 Y:2019 | 02 | 2019 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $5,310 | $18,709 | Implemented |
IP0112 # 05 Y:2019 | 05 | 2019 | USE PHOTOCELL CONTROLS | $403 | $35 | Implemented |
IP0112 # 11 Y:2019 | 11 | 2019 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $7,283 | $30,250 | Implemented |
IP0112 # 10 Y:2019 | 10 | 2019 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $11,070 | $21,274 | Implemented |
IP0112 # 09 Y:2019 | 09 | 2019 | INSULATE BARE EQUIPMENT | $674 | $945 | Implemented |
IP0112 # 07 Y:2019 | 07 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,905 | $5,340 | Implemented |
IP0112 # 06 Y:2019 | 06 | 2019 | INSTALL OCCUPANCY SENSORS | $21,079 | $3,360 | Implemented |
IP0112 # 03 Y:2019 | 03 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,835 | $130 | Implemented |
IP0112 # 01 Y:2019 | 01 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $23,973 | $5 | Implemented |
IP0111 # 04 Y:2018 | 04 | 2018 | INSTALL OCCUPANCY SENSORS | $1,101 | $893 | Implemented |
IP0111 # 09 Y:2018 | 09 | 2018 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $180 | $679 | Implemented |
IP0111 # 03 Y:2018 | 03 | 2018 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $780 | $217 | Implemented |
IP0111 # 01 Y:2018 | 01 | 2018 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $1,378 | $0 | Implemented |
IP0110 # 10 Y:2018 | 10 | 2018 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $7,081 | $30,250 | Implemented |
IP0110 # 06 Y:2018 | 06 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,905 | $5,340 | Implemented |
IP0110 # 03 Y:2018 | 03 | 2018 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,835 | $130 | Implemented |