Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
744
matching recommendationsNAICS | 332812 | Metal Coating, Engraving (except Jewelry and Silverware), and Allied Services to Manufacturers |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AM0943 # 10 Y:2025 | 10 | 2025 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,290 | $0 | n/a |
AM0943 # 07 Y:2025 | 07 | 2025 | USE OPTIMUM THICKNESS INSULATION | $4,270 | $6,012 | n/a |
AM0943 # 06 Y:2025 | 06 | 2025 | USE OPTIMUM THICKNESS INSULATION | $5,170 | $170 | n/a |
AM0943 # 08 Y:2025 | 08 | 2025 | USE SYNTHETIC LUBRICANT | $539 | $0 | n/a |
AM0943 # 05 Y:2025 | 05 | 2025 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,831 | $85 | n/a |
AM0943 # 04 Y:2025 | 04 | 2025 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $8,550 | $0 | n/a |
AM0943 # 03 Y:2025 | 03 | 2025 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $46,500 | $15,000 | n/a |
AM0943 # 02 Y:2025 | 02 | 2025 | PREHEAT COMBUSTION AIR WITH WASTE HEAT | $25,900 | $50,000 | n/a |
AM0943 # 01 Y:2025 | 01 | 2025 | USE SOLAR HEAT TO MAKE ELECTRICTY | $43,210 | $493,838 | n/a |
LE0594 # 04 Y:2025 | 04 | 2025 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $42,706 | $75,000 | n/a |
LE0594 # 02 Y:2025 | 02 | 2025 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,393 | $1,560 | n/a |
LE0594 # 05 Y:2025 | 05 | 2025 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $8,003 | $22,000 | n/a |
LE0594 # 07 Y:2025 | 07 | 2025 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $4,206 | $17,020 | n/a |
LE0594 # 06 Y:2025 | 06 | 2025 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $5,643 | $16,923 | n/a |
LE0594 # 01 Y:2025 | 01 | 2025 | INSTALL TIMERS AND/OR THERMOSTATS | $3,456 | $0 | n/a |
LE0594 # 08 Y:2025 | 08 | 2025 | USE FOSSIL FUEL POWERED GENERATOR DURING PEAK DEMAND PERIODS | $15,529 | $74,000 | n/a |
LE0594 # 03 Y:2025 | 03 | 2025 | RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | $2,962 | $2,500 | n/a |
LE0587 # 04 Y:2025 | 04 | 2025 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $667 | $2,000 | n/a |
LE0587 # 01 Y:2025 | 01 | 2025 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,438 | $0 | n/a |
LE0587 # 06 Y:2025 | 06 | 2025 | PREHEAT COMBUSTION AIR WITH WASTE HEAT | $4,080 | $15,000 | n/a |
LE0587 # 02 Y:2025 | 02 | 2025 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $10,795 | $1,400 | n/a |
LE0587 # 05 Y:2025 | 05 | 2025 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $1,851 | $6,801 | n/a |
LE0587 # 07 Y:2025 | 07 | 2025 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $735 | $2,997 | n/a |
LE0587 # 03 Y:2025 | 03 | 2025 | USE SOLAR HEAT TO MAKE ELECTRICTY | $58,495 | $190,400 | n/a |
UU0263 # 01 Y:2025 | 01 | 2025 | INSTALL COMMON HEADER ON COMPRESSORS | $7,583 | $46,630 | Implemented |