Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,737
matching recommendationsNAICS | 333 | Machinery Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UK1314 # 06 Y:2013 | 06 | 2013 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $2,594 | $0 | Implemented |
UK1314 # 07 Y:2013 | 07 | 2013 | TURN OFF EQUIPMENT WHEN NOT IN USE | $1,662 | $650 | Implemented |
UK1314 # 08 Y:2013 | 08 | 2013 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $798 | $700 | Implemented |
UK1314 # 09 Y:2013 | 09 | 2013 | USE PHOTOCELL CONTROLS | $328 | $592 | Implemented |
UK1314 # 10 Y:2013 | 10 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $690 | $690 | Implemented |
TT0112 # 02 Y:2013 | 02 | 2013 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,630 | $2,600 | Implemented |
TT0112 # 03 Y:2013 | 03 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $145 | $700 | Implemented |
TT0112 # 04 Y:2013 | 04 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,571 | $25,960 | Implemented |
TT0112 # 05 Y:2013 | 05 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,801 | $5,122 | Implemented |
TT0112 # 06 Y:2013 | 06 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $54 | $394 | Implemented |
LE0355 # 04 Y:2013 | 04 | 2013 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,970 | $2,640 | Implemented |
LE0355 # 07 Y:2013 | 07 | 2013 | INSTALL TIMERS AND/OR THERMOSTATS | $1,174 | $1,200 | Implemented |
LE0355 # 09 Y:2013 | 09 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,879 | $1,000 | Implemented |
OK0862 # 01 Y:2013 | 01 | 2013 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $2,733 | $0 | Implemented |
OK0862 # 03 Y:2013 | 03 | 2013 | INSTALL OCCUPANCY SENSORS | $3,000 | $2,520 | Implemented |
MZ0130 # 01 Y:2013 | 01 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,164 | $1,000 | Implemented |
MZ0130 # 03 Y:2013 | 03 | 2013 | REPAIR FURNACES AND OVEN DOORS SO THAT THEY SEAL EFFICIENTLY | $17,041 | $5,200 | Implemented |
MZ0130 # 04 Y:2013 | 04 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,911 | $36,015 | Implemented |
MZ0113 # 01 Y:2013 | 01 | 2013 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $17,414 | $8,758 | Implemented |
MZ0113 # 03 Y:2013 | 03 | 2013 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $7,609 | $1,000 | Implemented |
MZ0113 # 04 Y:2013 | 04 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,882 | $1,698 | Implemented |
MZ0113 # 05 Y:2013 | 05 | 2013 | INSTALL SPECTRAL REFLECTORS / DELAMP | $3,613 | $4,973 | Implemented |
MZ0113 # 06 Y:2013 | 06 | 2013 | UPGRADE CONTROLS ON COMPRESSORS | $3,575 | $3,500 | Implemented |
MZ0113 # 07 Y:2013 | 07 | 2013 | CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE | $1,948 | $50 | Implemented |
MZ0113 # 08 Y:2013 | 08 | 2013 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,620 | $900 | Implemented |